|
Post by burkitt on Jan 11, 2024 9:51:28 GMT
However articulated trains need shorter carriages, because the distance between bogie centres is constrained. Therefore an articulated train of the same total length would have more carriages, and only a small saving in bogies. For example, on the Piccadilly a 73TS has six cars with a total of twelve bogies, while the articulated 24TS has nine cars with ten bogies. An articulated DLR train equivalent to the B23 would need at least six cars/seven bogies, but looking at the bogie centres on the existing units I think eight cars / nine bogies is more likely.
|
|
|
Post by spsmiler on Jan 11, 2024 17:56:21 GMT
|
|
|
Post by jimbo on Jan 11, 2024 19:56:02 GMT
The new trains probably had to have more bogies to share the extra weight of air-con kit without increasing axle weight on some of the historic structures.
|
|
rincew1nd
Administrator
Junior Under-wizzard of quiz
Posts: 10,286
|
Post by rincew1nd on Jan 13, 2024 16:10:50 GMT
Lets be honest, we all sit at the front of the DLR so we can pretend to be driving. Copenhagen metro has had pseudo control panels under the front windows for a while now: (Embedded tweet above shows this)
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Jan 14, 2024 22:59:55 GMT
"Inflexible, fixed rakes" is regarded as an advantage in this case. The inter-unit gaps waste space that could be used for passengers and the couplers are wearing out from coupling and uncoupling. The DLR needs more capacity, the only reason they don't run all the current services as three-car trains is they haven't got enough rolling stock to do so at the desired frequency. Previously passenger circulating capacity at Bank was a limiting factor on running more trains there, but this has now been resolved.
Regarding non-articulated stock. Remember that the DLR has some very tight curves and steep gradients. Articulation points are inherently less flexible than couplers between cars, so this may have been a factor.
|
|
|
Post by ijmad on Jan 15, 2024 13:11:38 GMT
90% of modern trains are 'inflexible fixed rakes' whether it be the S-Stock, the NTFL, the B23s, and the Aventras/Desiros/FLIRTS on the main line or whatever.
I think the horse has well and truly bolted on that front.
|
|
|
Post by jimbo on Jan 15, 2024 19:41:48 GMT
I guess cab systems are a major cost of a train, and having a spare one or two riding around in a train much of the day is not a good use of funds!
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Jan 15, 2024 20:10:30 GMT
Cabs are also a major use of space, with (per cab) 0-2 staff members and equipment taking the same area as circa 4 seated passengers. Coupling and uncoupling units is costly in terms of time, capacity and money so, especially on metro services it is cheaper to run a train at a fixed length all day than to add or remove cars to account for expected capacity, so the cost-benefit calculation for cabs is usually negative. I suspect this is even more so post-pandemic given the relative flattening of peaks. In the days of steam locos, labour was cheaper, you had to shunt locos anyway and there was a much greater difference between the type of maintenance required by locos and carriages, so the equation was very different.
|
|
rincew1nd
Administrator
Junior Under-wizzard of quiz
Posts: 10,286
|
Post by rincew1nd on Jan 15, 2024 22:56:21 GMT
90% of modern trains are 'inflexible fixed rakes' whether it be the S-Stock, the NTFL, the B23s, and the Aventras/Desiros/FLIRTS on the main line or whatever. I think the horse has well and truly bolted on that front. I think either your choice of 90% is low or your definition of "modern" very loose. The TransPennine Express Mk5 stock worked in fixed rakes, though I'm not sure about the Caledonian Sleeper carriages. Prior to that it's the 1990s Mk4 stock, which operate in fixed rakes. Bringing it back on topic for this forum, everything currently operates as fixed rakes, indeed on the Central Line cabs have been harvested for parts and are now condemned to being within a train.
|
|
|
Post by ijmad on Jan 15, 2024 23:27:47 GMT
90% of modern trains are 'inflexible fixed rakes' whether it be the S-Stock, the NTFL, the B23s, and the Aventras/Desiros/FLIRTS on the main line or whatever. I think the horse has well and truly bolted on that front. I think either your choice of 90% is low or your definition of "modern" very loose. Yeah lack of knowledge on my part, I wasn't sure about the 2009TS or the Nova3's for example. Ta for the extra info.
|
|
|
Post by brigham on Jan 16, 2024 8:31:58 GMT
It looks as though the biggest problem with articulated stock, ie fixed rakes, is no longer an issue.
We should be able to look forward to some reduced-weight, highly-flexible trains for the DLR in future, once the message gets out.
|
|
|
Post by t697 on Jan 16, 2024 18:44:05 GMT
The Greater Anglia Aventras are in 5 car sets that couple to form 10 cars for busier services so there's still a bit of coupling/uncoupling in service. Liverpool St mid to late afternoon if you are interested. Replaced trains with shorter cars in 4 car units that could make 8's or 12's.
|
|
|
Post by jimbo on Jan 16, 2024 19:21:51 GMT
Tube train cabs of the 1938 era were only a couple of feet deep, so narrow that I had to ride side-saddle to get my knees within the control desk. They only really featured a brake handle and a power controller. Modern trains provide a comfortable workstation, with controls for radio communications, passenger address, signaling interface, platform interface, safe door operation, etc etc. So they take up more space, and require a lot more investment in equipment which then requires maintenance. The fewer the better in a train. It's hard to imagine a time when shorter trains could operate as demand has increased throughout the day, and off-peak service intervals still allow travelers to turn-up and go. In the past a 30-minute service off-peak might have met demand on a branch, but was operated as a 15-minute service of half-length trains.
|
|
|
Post by ijmad on Jan 16, 2024 20:07:42 GMT
Steering back to DLR topics, shorter trains more often was the big change in the May 2023 timetable wasn't it. I assume that once the B23s arrive in force, more or less every service will be running full length, since the B23s can't be split and they should have enough trains to always run 3x of the older stock.
|
|
|
Post by goldenarrow on Jan 16, 2024 21:17:10 GMT
Almost but not quite. Even after the full deployment of the B23’s, including the extra Housing Infra Fund funded trains, the Stratford Int - Beckton service is planned to continue to be operated by short formed B07’s all day.
|
|
|
Post by ijmad on Jan 17, 2024 0:56:36 GMT
Interesting!
Any idea how many units that service needs? Interested to know how many B07s that leaves.
Will the remaining B07s just run in threes everywhere and get mixed in with the B23s or is there another specific route we'll see the rest allocated to eventually?
|
|
|
Post by thinlizzy on Jan 17, 2024 15:31:13 GMT
At the moment, I believe B23s will only operate from Beckton depot, so all "runs" that operate from Poplar will be B2007s. On the current schedule, the only route where all the trains operate out of Poplar depot is the Stratford (High Level) route. On all other routes, trains operate from both Poplar and Beckton depots.
This is, of course, subject to change
|
|
|
Post by goldenarrow on Jan 17, 2024 17:36:34 GMT
Interesting! Any idea how many units that service needs? Interested to know how many B07s that leaves. Will the remaining B07s just run in threes everywhere and get mixed in with the B23s or is there another specific route we'll see the rest allocated to eventually? I’ve only got partial notes to hand, but I *think* that Stratford Int - Beckton requires 6/8 trains off-peak/peak. In addition, the end-state plan puts the remaining B07s all as 3-car sets working Tower - Beckton (6/8 trains off-peak/peak) and Stratford Int - Woolwich (5/7 trains off-peak/peak), the latter being a mixed service with B23s. There are at least three stock/formation rotations before we get to that point though, so plenty of changes between now and 2026.
|
|
|
Post by ijmad on Feb 19, 2024 12:17:11 GMT
Anyone heard the latest? The B23s seemed to be out and about during this weekend's closure, wondered if anyone knew whether we might see them in service next month as was hinted.
|
|
|
Post by jimbo on Feb 21, 2024 2:34:22 GMT
[TfL Investment programme report Quarter 3 2023/24 (17 September to 9 December 2023)]
I wonder why it was decided to continue DLR train production whilst the original trains are under test. Problems discovered may require the modification of all 22 trains completed so far! Meanwhile only two Piccadilly Line trains are completed and under test. Lessons leant can be incorporated into the main production run. Both fleets are ordered by TfL!
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Feb 21, 2024 4:29:19 GMT
The two parties (customer and manufacturer) will have agreed a delivery schedule for test train(s) and production trains, but I expect that the choice of when to manufacture them is entirely the manufacturer's. The customer will only make the final payments for the train once the agreed acceptance criteria are met, and so it's not generally going to be financially relevant to them whether the trains are modified post-production line or not (unless there are significant differences in life expectancy and/or maintenance requirements).
Whoever makes the decision, it will include consideration of the likelihood and likely significance of required hardware modifications. My guess is that the DLR's much more modern, relatively compact, relatively homogenous network was seen as having a lower risk of this than the Piccadilly line. The differences from the manufacturer's platform (and how established that platform is) will also make a difference.
|
|
|
Post by jimbo on Mar 6, 2024 4:51:47 GMT
At the end of May there were 12 trains completed (see above), and 25 now, so 13 built in 5 months. By the time the first train enters service in March 2024 they will have completed about 38 of the 54, with the total build finished around the end of the calendar year. I can't recall a previous build that got so far ahead of entry to service. That requires a lot of costly storage space. And hopefully the current testing doesn't reveal fixes required for the whole fleet! The 2009TS pre-production pair of trains were scrapped after testing since so many modifications were required for the fleet build that it was cheaper to start again! ..... Some doubt on build rate as latest report is 22 trains now built, but taking 13 built in 5 months, will be introduced to service at 10 in 5 months, or two trains per month, so no faster than build rate. Won't catch up the backlog, and 54 trains will take 27 months to enter service until mid-2026. "Manufacturing of the new rolling stock in Spain is continuing, with 22 trains completed." [ TfL Finance Report, Period 11, 2023/24, Management results from 1 April 2023 – 3 February 2024] So it looks like manufacturing of the new rolling stock in Spain is not actually continuing, with no change in the number built since my 30 November post, over three months back! Well at least two months before period end 3 February 2024. Addendum: I found the number 22 in Investment programme report Quarter 2 2023/24 (25 June to 16 September 2023) p.18/76, so no new completion to 3 February 2024, or 140 days, 4 months, 2 weeks and 4 days by my calculator!
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Apr 17, 2024 18:25:20 GMT
I've not had chance to watch this yet, but it has been recommended to me
|
|
|
Post by jimbo on Jun 5, 2024 0:42:05 GMT
Some doubt on build rate as latest report is 22 trains now built, but taking 13 built in 5 months, will be introduced to service at 10 in 5 months, or two trains per month, so no faster than build rate. Won't catch up the backlog, and 54 trains will take 27 months to enter service until mid-2026. "Manufacturing of the new rolling stock in Spain is continuing, with 22 trains completed." [ TfL Finance Report, Period 11, 2023/24, Management results from 1 April 2023 – 3 February 2024] So it looks like manufacturing of the new rolling stock in Spain is not actually continuing, with no change in the number built since my 30 November post, over three months back! Well at least two months before period end 3 February 2024. Addendum: I found the number 22 in Investment programme report Quarter 2 2023/24 (25 June to 16 September 2023) p.18/76, so no new completion to 3 February 2024, or 140 days, 4 months, 2 weeks and 4 days by my calculator! Production of new DLR trains is underway again, with "To date, 30 new DLR trains have been built and are in various stages of testing." (TfL Commissioner’s report - June 2024)
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Jun 5, 2024 17:46:57 GMT
|
|
|
Post by spsmiler on Jun 5, 2024 18:12:12 GMT
Has staff training actually began ... so that there can be a great PR exercise about this investment in new rolling stock even if only a 'just a few' can actually enter passenger service?
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,786
|
Post by Chris M on Jun 5, 2024 19:26:02 GMT
My understanding is that the issues aren't related to the physical availability of the trains - all but about 11 could be in London now if they were all built (stabling space being the issue with those 11). The issue is that mechanical and/or software problems mean that has not been verified they are safe and ready to operate. It is unlikely that staff training can begin before the issues are resolved and testing has been completed, and public service definitely cannot begin before testing is complete.
|
|
|
Post by spsmiler on Jun 6, 2024 22:51:27 GMT
Thanks Chris MAnd also eek! I hope we are not going to see a long delay saga similar to the Class 710 trains on the Goblin service
|
|
|
Post by spsmiler on Jun 12, 2024 22:20:33 GMT
Earlier today I had a little chat today with a DLR PSA.
Anyway, yes there are B23 trains here - but we knew that. He reckons it could be 2025 before they start carrying passengers. So far even the staff trainers have not been trained on them!
What was not discussed is the reason for the delay. I felt that it was better to not ask and he did not volunteer any information.
Alas, the days when new rolling stock arrived on Monday morning and was carrying passengers the same afternoon are long past.
|
|
|
Post by thinlizzy on Jun 13, 2024 23:14:39 GMT
Earlier today I had a little chat today with a DLR PSA. Anyway, yes there are B23 trains here - but we knew that. He reckons it could be 2025 before they start carrying passengers. So far even the staff trainers have not been trained on them! What was not discussed is the reason for the delay. I felt that it was better to not ask and he did not volunteer any information. Alas, the days when new rolling stock arrived on Monday morning and was carrying passengers the same afternoon are long past. There is a training team for the new trains. From what I understand, next B23 will arrive next month
|
|