|
Post by MoreToJack on Feb 18, 2020 21:28:39 GMT
That doesn’t sound right considering that Bombardier built the trains.
|
|
|
Post by crusty54 on Feb 19, 2020 2:21:02 GMT
That doesn’t sound right considering that Bombardier built the trains. Was told by a Siemans signalling engineer who was working on the trains whilst we were on a track access course together at Plumstead.
|
|
|
Post by goldenarrow on Mar 4, 2020 18:55:26 GMT
A snippet of dynamic testing in this video showing wrong road running between Farringdon, Fisher Street Emergency Crossover and Tottenham Court Road.
|
|
|
Post by brigham on Mar 5, 2020 8:58:39 GMT
Note overhead line pickup.
Must be intended for through running on the Great Northern & City!
|
|
|
Post by crusty54 on Mar 5, 2020 9:15:24 GMT
Note overhead line pickup. Must be intended for through running on the Great Northern & City! It's all overhead. The initial testing was all done on one track so bi-directional running was needed. The illuminated panels above the doors are capable of showing trains in the wrong direction.
|
|
|
Post by jimbo on Mar 5, 2020 19:13:27 GMT
Can Fisher St crossover hold a train? Is there anywhere to hide a defective train in the tunnel section?
|
|
|
Post by goldenarrow on Mar 5, 2020 20:23:47 GMT
Can Fisher St crossover hold a train? Is there anywhere to hide a defective train in the tunnel section? I’d assume not based on the fact that there are no TVM markers in the section of track between the two sets of points for Fisher St and Whitechapel only before and after. The sidings west of Paddington would be the only place on the combined core section to keep a train out of the way but of course that’s in the open.
|
|
|
Post by superteacher on Mar 5, 2020 20:30:57 GMT
There are sidings at Abbey Wood, but if there is a problem on that branch, they would have to send trains up to Ilford depot or Chadwell Heath reversing siding.
|
|
|
Post by silenthunter on Mar 5, 2020 21:22:20 GMT
Note overhead line pickup. Must be intended for through running on the Great Northern & City! It's all overhead. The initial testing was all done on one track so bi-directional running was needed. The illuminated panels above the doors are capable of showing trains in the wrong direction. They're using conductor rail instead of standard wires, BTW.
|
|
|
Post by crusty54 on Mar 5, 2020 22:13:17 GMT
It's all overhead. The initial testing was all done on one track so bi-directional running was needed. The illuminated panels above the doors are capable of showing trains in the wrong direction. They're using conductor rail instead of standard wires, BTW. Solid overhead is really the standard in tunnels nowadays.
|
|
|
Post by superteacher on Mar 10, 2020 21:40:08 GMT
|
|
|
Post by Dstock7080 on Mar 24, 2020 12:57:25 GMT
|
|
|
Post by silenthunter on Mar 24, 2020 14:47:28 GMT
Makes sure. Another month or so isn't going to make a huge bit of difference at this stage...
|
|
|
Post by bruce on Mar 24, 2020 16:22:02 GMT
|
|
|
Post by Deep Level on Apr 23, 2020 0:44:11 GMT
Custom House is the first central section station to be completed and handed over to TfL:
To be honest that surprised me as although it's a surface station I actually thought Canary Wharf was pretty much done.
|
|
|
Post by jimbo on Apr 23, 2020 4:06:07 GMT
I think we heard that Canary Wharf was finished so early, it doesn't fully meet current standards and needs some modifications!
|
|
|
Post by crusty54 on Apr 23, 2020 7:32:28 GMT
I think we heard that Canary Wharf was finished so early, it doesn't fully meet current standards and needs some modifications! This is correct. Farringdon is almost at the handover point.
|
|
|
Post by goldenarrow on Jun 2, 2020 14:30:17 GMT
Was listening in to the TfL Board Meeting today whilst doing some baking, some extra details came out that aren't in the agenda papers.
In addition to Custom House station being handed over to Rail for London, six shafts and portals have followed suit.
All core stations bar Bond Street are now complete to an acceptable standard to commence trial running. Bond Street is expected to be ready in 4-5 weeks.
Major questions remain over the push to get trial running underway before the year is out. At the time the safe stop was implemented and access was removed, it was estimated that only seven further tests were required to get the signalling software to an acceptable level of functionality for trial running.
Dynamic testing resumed this weekend past with a regression test, signalling software verification is expected to be completed in the next 4-6 weeks. This provides an assurance platform for certified use of trains in the core. A further software drop is planned for this Autumn aimed at addressing reliability and functionality.
Another risk quoted by Mark Wild was scenario testing, ventilation noise, smoke suppression and track dampening effectiveness etc. This form of testing was at around 40% completion at the time of the safe stop. To date this is now at 60%. A blockade of the core between this August and September is planned in order to recoup some of the lost time in this regard.
Plans are afoot for the early handover of Crossrail assets shared with London Underground for example the ticket hall at Moorgate, dates are TBC whilst the impact of how socially distant working will affect the outstanding works to be completed at the four stations concerned.
Following the lengthenings out on TfL Rail West, commencement of 345 airport services was stated as happening, "in the next short number of weeks when the appropriate training is completed and the various verification is received".
|
|
|
Post by bassmike on Jun 2, 2020 16:49:14 GMT
All very well to hand over to Tfl, but the way things are they probably can't afford it.
|
|
|
Post by Chris L on Jun 2, 2020 17:28:17 GMT
Handover of Moorgate ticket hall would allow a gate line to be re-instated and the temporary entrance/exit removed.
It could allow step free access to the Circle/H&C/Met platforms if the lifts are commissioned.
Station handovers also mean that the systems and equipment can be tested.
|
|
|
Post by hptraveller on Jun 2, 2020 18:22:27 GMT
All very well to hand over to Tfl, but the way things are they probably can't afford it. I don't think TfL would have the legal option of saying "Sorry guv, can't afford it now, you can sell it to someone else!". TfL will want to get the core running as soon as reasonably possible, because the fares and other revenue will be critical to offset the ongoing operational costs that can't be avoided (station staff, drivers, train leasing etc).
|
|
|
Post by jimbo on Jun 20, 2020 1:14:28 GMT
Network Rail news June 17, 2020 "TfL works to lengthen platforms 16 and 17 at Liverpool Street will begin over the Christmas period to make more platforms available for the new, longer Elizabeth line trains; Network Rail works for the Crossrail programme will continue with station upgrades taking place at Ilford and Romford this autumn." Does Elizabeth line refer to the service and Crossrail refer to the infrastructure? See: www.networkrail.co.uk/news/major-improvement-work-to-be-rolled-out-across-anglias-rail-network/
|
|
|
Post by goldenarrow on Jun 20, 2020 12:22:15 GMT
jimbo , Effectively yes, Crossrail is the construction arm of the project which will morph into the Elizabeth line which is the service being offered over said infrastructure. That hasn't stopped the terms being butchered at every level thanks to the changes we've seen over the past five years!
|
|
|
Post by silenthunter on Jun 20, 2020 12:59:05 GMT
Crossrail is also the 'mode'.
|
|
|
Post by phil on Jun 20, 2020 13:10:23 GMT
It's all overhead. The initial testing was all done on one track so bi-directional running was needed. The illuminated panels above the doors are capable of showing trains in the wrong direction. They're using conductor rail instead of standard wires, BTW. Not quite true - the actual conductor is still copper wire as per 'traditional' overhead line systems - its smoothness and electrical properties not having yet been bettered. The main change is rather than the conductor wire be suspended from a flexible Catenary system, it is clipped to a solid bar structure making the structure robust yet simple to install. This contrasts with true 'conductor rail' systems where the pick up on the train actually rubs along the rail surface.
Note as per traditional overhead systems, the bar (and thus the copper contact wire) wiggles from side to side as it goes thus avoiding wearing a grove in the pantograph head.
|
|
|
Post by phil on Jun 20, 2020 13:16:40 GMT
Network Rail news June 17, 2020 "TfL works to lengthen platforms 16 and 17 at Liverpool Street will begin over the Christmas period to make more platforms available for the new, longer Elizabeth line trains; Network Rail works for the Crossrail programme will continue with station upgrades taking place at Ilford and Romford this autumn." Does Elizabeth line refer to the service and Crossrail refer to the infrastructure? See: www.networkrail.co.uk/news/major-improvement-work-to-be-rolled-out-across-anglias-rail-network/Interesting - but if i recall correctly the works at Liverpool Street will reduce the number of platforms available so either they are banking on train services still being Covid reduced in 6 months time or else there will have to be a thinning out of TfL Rail services to Shenfield to suit the reduced number of platforms at Liverpool Street High Level.
As has been noted before NR are not in a position to simply wait till Crossrail is ready as the Liverpool Street works are tied in with lots of other things (in particular demands on resources) happening around the rest of the country.
|
|
|
Post by silenthunter on Jun 20, 2020 13:23:41 GMT
There would be 15 other platforms available, five in the relevant half of the station.
|
|
|
Post by Chris L on Jun 20, 2020 13:49:21 GMT
There would be 15 other platforms available, five in the relevant half of the station. Some of which are used by other services.
|
|
|
Post by superteacher on Jun 20, 2020 15:42:33 GMT
There would be 15 other platforms available, five in the relevant half of the station. Some of which are used by other services. During peak times, all platforms are used to capacity.
|
|
|
Post by phil on Jun 20, 2020 15:52:13 GMT
There would be 15 other platforms available, five in the relevant half of the station.
Liverpool Street station is used by more than TfL rail!
It has been made clear in the past that the remodelling work would permanently reduce the capacity for TfL rail services and thus would be done after crossrail was open when some services could be diverted away.
If crossrail won't be opening till the middle of next year, yet capacity at Liverpool street is going to be reduced then something has got to give and cancelling GA services to make room isn't one of them*.
Using 'other platforms' is NOT an option (or otherwise it would already be happening)
The only logical deduction is that TfL rail services will have to become less frequent from this winter till crossrail opens - but will TfL have the guts to admit it (and all the bad PR that goes with it)?
* The national rail network is not TfLs plaything like the tube or DLR. It cannot go round demanding it gets priority or things are done when it suits them however much it wants to.
|
|