|
Post by bassmike on Jan 26, 2019 13:11:52 GMT
Just back from a ride on one. And it did whizz through Old Street and Essex Road without stopping. Glad it wasn't in the opposite direction!
|
|
|
Post by melikepie on Jan 27, 2019 15:27:05 GMT
I still wonder if when all the 717s are in service and all 313s replaced, it still seems like there will hardly any spare capacity with the new timetable if anything goes wrong
|
|
|
Post by norbitonflyer on Jan 27, 2019 16:26:25 GMT
The Great Northern fleet of 313s is now 44 units, enough for 22 six car trains - although I don't know if they are still all serviceable. There are to be 25 new six-car class 717 units. Of course, unlike a complete six car unit, three car units can be juggled to make one good six car train out of two failed ones by using the good unit from each one.
|
|
|
Post by fleetline on Jan 27, 2019 17:31:53 GMT
[ It is much more common to fail to get the pan down and change onto DC than the other way That is probably not surprising, given that it couldn't have entered service from the depot if the pan was stuck down, so any fault would have had to arise in the relatively short time the train had been in the hole. But if it did fail to rise, the unit would effectively be trapped in the Drayton Park- Moorgate section until it was either fixed or dragged out. Where would it go in the meantime - presumably one of the platforms at Moorgate? Can Moorgate cope with a full service with one platform out of action? With the 313s, such a failure would usually be easy to remedy as each 3-car unit has its own pantograph and if the pantograph fails to raise on one of them, the other unit can pull (or push) it out. Not only is the 717 one unit, but (unlike the 700s) it only has one pantograph................ I seem to recall that the 319s had some problems in the early day of Thameslink, because they used a similar system to the 313s (at the time the only other dual voltage units on BR), but the AC components were not used to being idle for such extended periods as the 319s required (round trips to Brighton, not to mention depot visits to Selhurst) and they sometimes refused to raise the pan when they got to AC country at Farringdon. No NCL cannot cope with a platform out at Moorgate. Requires 50% of the service diverted to Kings Cross. Couple of failures of the 313s last week proved this point rather well. A 717 failing to changeover means NCL shuts. Note one 313 failing to changeover requires the other one to haul it and creates problems too and due to the metro nature ends up with some services diverted.
|
|
|
Post by norbitonflyer on Jan 27, 2019 17:43:37 GMT
A 717 failing to changeover means NCL shuts. Would another unit be able to push it out?
|
|
|
Post by fleetline on Jan 27, 2019 17:45:40 GMT
A 717 failing to changeover means NCL shuts. Would another unit be able to push it out? Yes. Although if the unit is dead then its a 5mph speed restriction as best. Its worth noting that other 5 car trains only have one pan.
|
|
|
Post by phil on Jan 28, 2019 18:43:38 GMT
Folk should remember that there is a crossover north of Drayton Park allowing a train to depart north from what is normally the Southbound platform.
While obviously it will cause disruption, its quite possible that should the unit fail to change onto DC then it could be terminated at Drayton Park and driven back north under AC. This is the standard procedure in the Thameslink core should a unit fail to swap AC-DC or DC-AC as the 12 car units are too long for the Smithfield sidings and both the traction supplies overlap between City Thameslink and Farringdon with suitable crossovers provided in this section.
The bigger problem at Drayton Park is if the unit fails to change from DC to AC, as rescuing it will most likely require the following unit to be used to push the defective one up to Finsbury Park.
|
|
|
Post by silenthunter on Jan 28, 2019 21:25:19 GMT
How many 717s are running now? Does anyone know the schedules for them as I'm looking to 'bash' one on Wednesday afternoon.
|
|
|
Post by norbitonflyer on Jan 29, 2019 8:11:01 GMT
Two units running I think. The only runs in passenger service last week were at 1037, 1137 and 1337 from Moorgate to Gordon Hill. (2G82, 2G72, 2G74). The 1237 departure, and all the return workings from Gordon Hill to Moorgate, were empty stock (5Gxx, 5Jxx in Real Time Trains). Note also that the trains do not call at Old Street, Essex Road, Hornsey or Harringay
|
|
rincew1nd
Administrator
Junior Under-wizzard of quiz
Posts: 10,286
|
Post by rincew1nd on Jan 31, 2019 10:31:57 GMT
Mr Clinnick writes:
[Embed]
|
|
|
Post by alpinejohn on Feb 27, 2019 10:34:07 GMT
After looking at the video posted a short way upthread by Vinnielo, it strikes me that the door opening/release process on these trains may need further attention if it is not going to lead to extended station dwell times - especially on peak hour services.
At various stops it was clear the train had been stopped for several seconds before the "door release chime" could be heard - by which time passengers were starting to panic just in case the doors in their coach were somehow defective or disabled, and started to pass down the train to get to other doorways. I guess this may be just a teething issue and the delay may be reduced or eliminated once drivers become more accustomed to activating the relevant door release controls.
However what worries me is that something very similar was evident in the videos of the battery Class 230 runs in Scotland where again there was a very long period before there was any sign of doors being released despite the train being suitably berthed at a platform which extended well beyond the length of the train.
Is this new extended delay with the train stopped something dictated by the latest accessibility rules? Certainly I never recalled long delays before doors shot open when they were D-Stock running on the District - indeed sometimes they seemed to open almost instantly the train stopped?
Hopefully I am wrong and this is something which can be software engineered out. If the intention of the delay is to help vision impaired travellers locate the opening doors, then surely the delay could be avoided if PIS system was programmed to announce "we are approaching xxx station" together with a suitable announcement like "the doors will open on the right side of the train". This should obviate the need for any delay before the doors open once the train comes to a halt and the door chime to be triggered immediately.
Otherwise I fear TFLs attempts to increase service frequency on various tube lines will be largely negated and for instance passengers on the Victoria and other high frequency lines will see a dramatic impact on crowding especially in the peak hours due to extended platform dwell times.
|
|
|
Post by ducatisti on Feb 27, 2019 10:48:04 GMT
there's a time gap on the 710 too.
I think overall the dwell time will still come down as people can load faster onto them. (especially compared to 313s when people cluster in the vestibules and won't move down).
With regard to the 313s, there is one service path every day for a 3-car unit, which is an absolute pain when end up catching it at 7ish out of Finsbury park - I assume that means they don't have enough of them, not just that they like to keep commuters on their toes...
|
|
|
Post by spsmiler on Feb 27, 2019 11:41:03 GMT
Maybe because the driver has to ensure that the train has stopped in the correct position with all doors aligned to platforms?
What would be useful is for all doors to open automatically - especially at Moorgate and Highbury & Islington. This already happens on 700's at some Central London stations
|
|
|
Post by norbitonflyer on Mar 11, 2019 13:42:01 GMT
|
|
|
Post by silenthunter on Mar 11, 2019 14:35:01 GMT
The S Stock is Bombardier, this is Siemens.
|
|
|
Post by norbitonflyer on Mar 11, 2019 15:35:02 GMT
The S Stock is Bombardier, this is Siemens. I know, but they were essentially both required to solve the same problem - installing an evacuation system whilst still allowing the driver to see signals in confined stations. As a matter of interest, would there be the same sighting problems at those stations if the trains were S stock? (According to Wikipedia, an S7 is about 4 metres shorter than a 717).
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,767
|
Post by Chris M on Mar 11, 2019 16:24:47 GMT
Do you have a link for the story in a reliable source? In the Daily Mail it's more likely than not the author of the piece has wildly exaggerated a story out of something they've misunderstood.
|
|
rincew1nd
Administrator
Junior Under-wizzard of quiz
Posts: 10,286
|
Post by rincew1nd on Mar 11, 2019 16:45:40 GMT
If you want an entertaining half hour read the comments on this article, my favourite: [sic]
|
|
|
Post by goldenarrow on Mar 25, 2019 15:54:31 GMT
717006 was one of two units let loose today on a peak time service (2J20 0711 Gordon Hill to Moorgate) then working back on 2G22 (07:55 Moorgate - Gordon Hill).
At present two units are running on weekdays only, times below.
|
|
|
Post by t697 on Mar 25, 2019 17:22:00 GMT
The S Stock is Bombardier, this is Siemens. I know, but they were essentially both required to solve the same problem - installing an evacuation system whilst still allowing the driver to see signals in confined stations. As a matter of interest, would there be the same sighting problems at those stations if the trains were S stock? (According to Wikipedia, an S7 is about 4 metres shorter than a 717). There was a huge amount of work on sighting signals and other 'sighted assets' from S stock for their introduction. This meant lots of analysis, some asset relocation, some co-acting signals, lots of sighting runs and lots of platform integration testing. Bit of a surprise if the Class 717 project has not fully planned for the same thing. And you might be amazed how much had to be spent even for the S8 routes just for a train 2m longer and with the driver sitting further back with slightly narrowed sightlines.
|
|
roythebus
Pleased to say the restoration of BEA coach MLL738 is as complete as it can be, now restoring MLL721
Posts: 1,275
|
Post by roythebus on Mar 26, 2019 0:29:00 GMT
Latest news from the 34A Kings Cross FB group is that the new trains will be fitted with a 2nd man to assist the driver's signal sighting. that's progress for you. 4 stations or locations where the driver can't see the signals. what on erth do these designers get paid for, not designing trains for drivers to look out of?
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Mar 26, 2019 9:06:02 GMT
Latest news from the 34A Kings Cross FB group is that the new trains will be fitted with a 2nd man to assist the driver's signal sighting. that's progress for you. 4 stations or locations where the driver can't see the signals. what on erth do these designers get paid for, not designing trains for drivers to look out of? The trains were actually designed with in-cab signalling in mind - Network Rail have dropped the ball in not meeting timelines for installing it, and given the trains have been around since last autumn, Network Rail have also seemingly failed to re-site the existing signals in that time. Progress shouldn't be held back because of legacy infrastructure.
|
|
|
Post by aslefshrugged on Mar 26, 2019 9:30:55 GMT
Latest news from the 34A Kings Cross FB group is that the new trains will be fitted with a 2nd man to assist the driver's signal sighting. that's progress for you. 4 stations or locations where the driver can't see the signals. what on erth do these designers get paid for, not designing trains for drivers to look out of? The trains were actually designed with in-cab signalling in mind - Network Rail have dropped the ball in not meeting timelines for installing it, and given the trains have been around since last autumn, Network Rail have also seemingly failed to re-site the existing signals in that time. Progress shouldn't be held back because of legacy infrastructure. Add it to the list of projects that Network Rail have had to "pause" because they can't afford it.
|
|
|
Post by spsmiler on Mar 26, 2019 22:17:12 GMT
Now that they are in service I went for a spin - albeit only on the Northern City line between Highbury & Islington and Essex Road.
At the latter I filmed the same train going both ways, I did not film the door opening on the southbound journey as I was discussing the service with a member of staff who kindly advised me that the second train was running late (I had intended to travel on that!).
The second pass (northbound) also shows the mid-platform CCTV displays for driver only operation of single unit Class 313 trains. I do wonder why similar does not exist for 717's here - it would help with the sighting issues!
by the way, camera angles showing the remaining Network Southeast signage was not accidental. I wonder if this will eventually be vinyl covered - or simply removed? BR would have put station name signage at that location for a very good reason, this being that it helps passengers know where they are. It would be far better if Great Northern retained this feature,
Also, note the view from inside the 717 (at Essex Road) just before the doors close - the dado rail on the platform has been removed, leaving some previous tiling visible.
|
|
|
Post by phil on Mar 26, 2019 22:44:06 GMT
The second pass (northbound) also shows the mid-platform CCTV displays for driver only operation of single unit Class 313 trains. I do wonder why similar does not exist for 717's here - it would help with the sighting issues!
The 717s (like ALL new EMUs designed with the possibility of Driver Only Operation (DOO) in mind) have bodyside mounted cameras and in cab monitors rather than monitors and cameras mounted on platforms.
This approach facilitates the easy extension of DOO and also means less stuff to be vandalised by yobs or maintained by Network Rail.
The 313s (as with all such British Rail designed DOO EMUs, relied on the provision of platform mounted equipment - which, in the case of the 313s had to be duplicated to facilitate both 3 and 6car trains.
In any case the issue with the 717s is signal sighting from the cab - nothing to do with DOO equipment.
|
|
|
Post by ducatisti on Mar 28, 2019 14:34:53 GMT
I saw them out and about yesterday.
unfortunately I had to be at mailrail for 10, so I couldn't have caught one.
|
|
|
Post by goldenarrow on Apr 8, 2019 15:46:43 GMT
313026 has been the first of the 313 fleet to be sent to Newport for scrapping.
|
|
slugabed
Zu lang am schnuller.
Posts: 1,480
|
Post by slugabed on Apr 8, 2019 16:29:47 GMT
313026 has been the first of the 313 fleet to be sent to Newport for scrapping. Meanwhile,on the Goblin...
|
|
metman
Global Moderator
5056 05/12/1961-23/04/2012 RIP
Posts: 7,421
|
Post by metman on Apr 8, 2019 20:13:20 GMT
Sadly they are not an option as discussed in length on the London Overground section.
Sad to hear the old 313s are starting to go. What sort of rate of introduction are the 717s expected to have?
|
|
|
Post by ducatisti on May 31, 2019 8:39:30 GMT
(couldn't find the original thread, please move etc as appropriate) Now these are getting more common, I've started to notice little things about them.
On a super high-tec train, I have just noticed they have a lamp bracket on the right hand side of the front about half-way up to the side of the evacuation door.
It looks like it may be a retro-fit? Is it a requirement of the underground section?
I wonder if they still carry a lamp to put on there (presumably a rear lamp, and battery-powered I assume, not oil...)?
|
|