Post by A60stock on May 11, 2022 21:14:10 GMT
Does anyone know what work is carried out on the S8s as part of the major overhaul they're having at the moment, both externally and internally?
|
|
|
Post by Dstock7080 on May 12, 2022 5:43:29 GMT
|
|
|
Post by jimbo on May 12, 2022 6:00:42 GMT
The TfL Commissioner’s report on 3 February 2021 said that the first overhaul of S stock, which entered service between 2010 and 2012, has started with the S8 trains on the Metropolitan line, which have now completed around 1.25 million kilometres each. The work includes wheels, suspension, brakes, air and electrical systems, and cab seat. TfL expect to complete the overhaul of S8 stock by the end of 2022, after which the S7 fleet should be completed by 2026.
|
|