Post by Dom K on Jul 10, 2021 14:42:31 GMT
Hi Everyone
I use Tottenham Hale station every day and have seen the progress of f the rebuild of the station. It does seem to be taking a very long time (I’m sure there are good reasons eg COVID-19)
Does anyone know the ETA for the next phase of opening and/or full completion dates.
Thanks in advance
|
|
|
Post by goldenarrow on Jul 10, 2021 15:40:52 GMT
Late 2021 is the publicly stated completion date. This particular project has been besieged with set backs ranging from revenue concerns with Greater Anglia to possession times with Network Rail and of course the safe stop that came into force with the first COVID lockdown. Some of the issues pre-COVID where mentioned in the STAR and Tottenham Hale updates thread.
|
|
Dom K
Global Moderator
The future is bright
Posts: 1,831
|
Post by Dom K on Dec 10, 2021 13:47:58 GMT
Just an update
The new Tottenham Hale station building has partially opened this morning and the entrance/exit is currently the side entrance adjacent to the Greater Anglia entrance. The hoarding has been replaced by see through metal fencing which suggests the station building is almost complete.
|
|
|
Post by Dstock7080 on Dec 15, 2021 9:34:26 GMT
New entrance and ticket hall keys officially handed over to LU Seven Sisters Area Manager and operational Staff 11.30am yesterday.
|
|