Post by Dstock7080 on Jul 9, 2021 17:13:16 GMT
East Acton eastbound platform is to close for 5-months from 2 August 2021 so that major repairs can be undertaken. Westbound trains will continue to stop and passengers encouraged to travel to North Acton abs change.
|
|
|
Post by goldenarrow on Nov 16, 2021 17:34:15 GMT
The end date for these works have now slipped to mid-May 2022. Additionally the station will be closed in totality during Night Tube hours (01:00 - 04:45) when that resumes on 27 November.
|
|
|
Post by cudsn15 on Nov 17, 2021 9:02:32 GMT
Personally I am surprised they have lasted as long as this. I used East Acton daily for a few years between 2012 and 2016 and they were in a dreadful state then and you could see the supports under each opposite platform all over the place probably due to subsidence.
However - for the works to take 10 MONTHS is absolutely crazy. Whoever is doing this must be raking the money in.
|
|
|
Post by aslefshrugged on Nov 17, 2021 11:01:49 GMT
The last train through East Acton is at 01:15, Ealing Broadway to White City, the first train is 05:18, White City to Ealing Broadway. Between juice going off and juice coming back on there's maybe a couple of hours each night for the crew to get on site, do some work then clear out again.
|
|
|
Post by d7666 on Nov 17, 2021 13:54:45 GMT
Personally I am surprised they have lasted as long as this. I used East Acton daily for a few years between 2012 and 2016 and they were in a dreadful state then and you could see the supports under each opposite platform all over the place probably due to subsidence. However - for the works to take 10 MONTHS is absolutely crazy. Whoever is doing this must be raking the money in. OK I'll bounce that one back to you : how would you do it and keep the station open and or less time overall ?
|
|
|
Post by routew15 on Nov 19, 2021 9:11:59 GMT
Is it known if the works at East Acton include the westbound platform once the eastbound is complete?
|
|
|
Post by spsmiler on Nov 19, 2021 20:45:15 GMT
Personally I am surprised they have lasted as long as this. I used East Acton daily for a few years between 2012 and 2016 and they were in a dreadful state then and you could see the supports under each opposite platform all over the place probably due to subsidence. However - for the works to take 10 MONTHS is absolutely crazy. Whoever is doing this must be raking the money in. OK I'll bounce that one back to you : how would you do it and keep the station open and or less time overall ? The route through here was a four track railway, anyone who looks closely (from the street below the station) will notice that there are actually two bridges over the road ... although disinvestment has affected the twin track alignment formerly used by British Railways goods trains, I wonder whether the route is now 'too far lost' to allow a single track diversion around the station with the other track being aligned with the platform that is still open?
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,781
|
Post by Chris M on Nov 20, 2021 0:10:40 GMT
Are you asking whether the diversion would be physically or economically possible? I suspect the answers might not be the same.
|
|
brigham
Posts: 2,542
Member is Online
|
Post by brigham on Nov 22, 2021 8:59:48 GMT
Are you asking whether the diversion would be physically or economically possible? I suspect the answers might not be the same. It had occurred to me that the former avoiding-line formation could be used to rebuild the platform from the back. Otherwise, can a possession be obtained for the Eastbound road only?
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,781
|
Post by Chris M on Nov 22, 2021 12:22:01 GMT
Otherwise, can a possession be obtained for the Eastbound road only? I'm sure that a possession for the eastbound only could be obtained. However, as this would require single line working between White City and North Acton this would massively reduce capacity. Further as this would require use of the middle platform at both stations for eastbound through trains you would also be significantly reducing capacity on the whole line. Looking at Carto Metro's track map, at White City you would be able to turn some westbound trains via platform 1 and the siding, how many though I have no idea. West of the closure, the track layout is less convenient. I suspect you would run all the through trains on the Ruislip branch, turning some via P3, a mainline shunt on the eastbound before the East Acton closure, and back into P2 (I don't know if the signalling would permit this, whether the traction current sections would allow these movements while also being switched off through East Acton, and even if both were possible how many trains it could handle). If the Ealing branch was not suspended then about the best you could do would be bi-directional working of one train on the normal westbound, reversing in North Acton platform 1, perhaps with a second train in the other platform at Ealing Broadway allowing for longer layovers. You might in theory be able to run a train on the eastbound line, reversing from P3 between reversing Ruislip trains, but again I don't know if the signalling would permit this and it seems like it would have a very high potential for something to go wrong (like two trains meeting head on between North Acton station and junction). On top of that it would be very confusing for passengers and station staff, particularly at North Acton. While I don't know what level of service could be run in this way, I strongly suspect it is going to be something that could only be viable very off peak. From memory of @moretojack talking about setting up single line one-train-in-steam working on the Hammersmith branch of the H&C following Grenfell, and assuming the procedures are similar on the Central line, this is not something you do lightly and so would effectively restrict such operation to weekends. So given everything, it's definitely simpler for everyone (staff and customers), and probably better value overall to just close the line through East Acton completely.
|
|
Tom
Administrator
Signalfel?
Posts: 4,199
|
Post by Tom on Nov 22, 2021 19:19:45 GMT
It's not that easy to rebuild from the trackbed of the old WLR connection. There are several buildings in the way and a lot of vegetation clearance would be required.
With regard to the idea of having single line working, you just wouldn't do it. The signalling system wouldn't be able to support running at line speed without significant alterations, so the best you could hope for is 10mph in the wrong direction and you wouldn't be able to achieve even the Sunday frequencies. Remember after the Grenfell fire it was two trains 'locked in' on a single line with conventional signalling, this would be very different!
|
|
|
Post by Dstock7080 on Jul 14, 2022 15:18:09 GMT
East Acton eastbound is finally due to reopen Monday 22 August - once again rescheduled!
|
|
|
Post by xtmw on Sept 2, 2022 21:46:04 GMT
East Acton (eastbound) has been given another opening date. Sunday 19 September.
|
|
|
Post by xtmw on Sept 18, 2022 20:19:04 GMT
East Acton eastbound looks all good for opening tomorrow. Unless something changes last minute.
|
|
DWS
every second count's
Posts: 2,487
|
Post by DWS on Sept 19, 2022 5:12:43 GMT
East Acton eastbound platform has reopened today Monday 19 October 2022, is the westbound due to be rebuilt ?
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,781
|
Post by Chris M on Jan 30, 2023 14:06:09 GMT
I've just noticed that the Wikipedia article for East Acton is out of date regarding the platform closure, but I've not been able to find any source (other than DWS's post above) that states when the works were complete. Does anyone know of a reliable source that states this? There doesn't appear to be anything on the TfL website or in the local news.
|
|
|
Post by goldenarrow on Jan 30, 2023 14:36:17 GMT
The November 2022 issue of Underground News (731, page 702) states:
‘Reopened on Monday 19 September from the start of traffic’
|
|
DWS
every second count's
Posts: 2,487
|
Post by DWS on Jan 30, 2023 16:16:54 GMT
East Acton eastbound platform has reopened today Monday 19 October 2022, is the westbound due to be rebuilt ? I was wrong 19 October 2022 was a Wednesday, so it was 19 September, the day of our late Queens State Funeral.
|
|