|
Post by jimbo on Oct 8, 2020 19:26:58 GMT
It says “some” of the Jubilee line trains can be used on the Northern line. Why plan to buy 73 new trains, when the case for 27 trains to boost both lines couldn't be made in 2017? That included 17 for the Northern for 30tph, and even that wouldn't be achieved in the morning peak due to track economies. 36tph there would have required 44 extra trains in all. Whilst that suggests plenty of surplus old Jubilee trains, they may look the same but technically they are incompatible. So it makes sense to use the Jubilee trains on the shorter Edgware-Battersea via Embankment line, holding spare parts and maintaining them at Golders Green, which may leave few surplus. The current trains would serve the Barnet-Morden via Bank service with spares holdings and servicing at Morden depot. So the surplus trains are likely to be current Northern line stock.
It is not possible to completely split the two branches, since the start up northbound service via Charing Cross requires the first nine northbound trains from Morden before the first southbound arrives. In the meantime the Battersea overnight stabler can shuttle to and from Kennington, reversing via the loop anti-clockwise.
This plan would provide extra trains for free, but extra stabling and maintenance will be a big cost. All stabling was to be enlarged, and Finchley Central goods yard filled with stabling roads. But isn't this to be used for new housing now? (Details from Underground News Aug 2016 & Jan 2019.)
|
|
|
Post by nig on Oct 8, 2020 22:08:24 GMT
How you transfer stock from the jubilee to the northern line is there a crossover ?
|
|
|
Post by A60stock on Oct 8, 2020 22:25:35 GMT
Why would the northern line need the jubilee line trains? Surely the line would have far too many trains to maintain if this was the case? Does the line struggle to meet service levels with the current number of trains?
|
|
|
Post by goldenarrow on Oct 8, 2020 22:28:37 GMT
How you transfer stock from the Jubilee to the Northern line is there a crossover ? Trackwise, leave Neasden to join the Metropolitan line up to Rayners Lane then reversal onto the Piccadilly line down to King's Cross then reversal onto either direction of the Northern line (Bank Branch) via the King's Cross Loop.
|
|
|
Post by nig on Oct 8, 2020 23:12:53 GMT
Why would the northern line need the jubilee line trains? Surely the line would have far too many trains to maintain if this was the case? Does the line struggle to meet service levels with the current number of trains? They need extra trains for the Battersea extension and to increase the frequency obviously won't have all the jubilee line trains just enough to meet there needs
|
|
|
Post by jimbo on Oct 9, 2020 0:08:57 GMT
Why would the northern line need the jubilee line trains? Surely the line would have far too many trains to maintain if this was the case? Does the line struggle to meet service levels with the current number of trains? The resignalling upgrade only offered 24tph (the same as Picc Line before upgrade!), with 30tph south of Kennington. It struggled to meet demand south of Kennington, the most crowded section of tube line. Also struggles through Bank branch and inner area of Barnet branch. Demand growing at outer end of Edgware branch. With more trains could go to 30tph+ and 36tph south of Kennington, but more than 30tph apparently needs split of branches at Camden Town and therefore station reconstruction there. Although sub-surface lines promise 32tph over many flat junctions, so couldn't Camden grade separated junctions cope with more?
|
|
vincenture
Quiz tryhard, and an advocate for simpler, less complicated rail routes
Posts: 885
|
Post by vincenture on Oct 10, 2020 8:07:53 GMT
Why would the northern line need the jubilee line trains? Surely the line would have far too many trains to maintain if this was the case? Does the line struggle to meet service levels with the current number of trains? The resignalling upgrade only offered 24tph (the same as Picc Line before upgrade!), with 30tph south of Kennington. It struggled to meet demand south of Kennington, the most crowded section of tube line. Also struggles through Bank branch and inner area of Barnet branch. Demand growing at outer end of Edgware branch. With more trains could go to 30tph+ and 36tph south of Kennington, but more than 30tph apparently needs split of branches at Camden Town and therefore station reconstruction there. Although sub-surface lines promise 32tph over many flat junctions, so couldn't Camden grade separated junctions cope with more? I think it is more about junction conflicts at Camden Town since at the current configuration, Charing Cross branch trains will all go to High Barnet/Mill Hill East while Bank branch trains will all go to Edgware without clashing at that junction. Another problem is that I think the speedlimit between Kennington and Morden is not higher than 65km/h (with some anomalies) due to narrow tunnels so it takes a little longer to clear headways. Perhaps they should consider widening the tunnels along with Morden core section station upgrades? They also need to critically fix what’s happening between Borough and Elephant & Castle if they really have a choice there.
|
|
|
Post by alpinejohn on Oct 10, 2020 12:17:56 GMT
... I think it is more about junction conflicts at Camden Town since at the current configuration, Charing Cross branch trains will all go to High Barnet/Mill Hill East while Bank branch trains will all go to Edgware without clashing at that junction.... I think you will find the junction at Camden Town already allows the necessary flexibility for trains - look closely at the cutaway diagram here linkYes for passengers there can be a scary moment if trains simultaneously approach Northbound to the separate branch platforms as they do appear to come awfully close - but thus far they have never touched. The Camden Town problem is primarily about narrow cross platform connection tunnels and their (in)ability to handle an overnight doubling of the numbers of interchanging passengers and of course the related costs of updating the station to current safety standards. Currently regular northern line passengers travelling through this junction on either branch/direction will tend to consult the platform departure board and make a decision on whether it is best to just wait for the next direct service to their destination or hop on the first service and change (mostly at Camden Town) although in the southbound direction some choose to change at Euston where they also have the option of adjacent Victoria line services. Inherently if passengers decide to wait a few minutes for a direct service they will do that on the platform they intend to board the Northern line so all those waiting people will be spread along much of the line. In short this "passenger judgement" effect significantly lessens numbers of interchange passengers at Camden town as the waiting is spread along platforms on all the branches in all directions rather than concentrated at Camden Town. Right now the pointwork at Camden Town Junction could already be set to completely separate the routes into the Mordware and Batternet branches. The problem is that separating the two routes probably means that roughly 50% of passengers arriving at Camden Town will now need to change with obvious impact on platform dwell times as every arriving train is likely to see a rugby scrum as up to half the on-board passengers want to alight at the same time the platform will probably be thronged by equivalent numbers of interchanging passengers waiting to board. This sort of flow would be challenging on a modern well designed spacious below-ground layout - and yes TFL do indeed have an almost shovel ready design complete with additional wide cross passageways and additional surface access but they do not have the cash, so it is probably not going to happen soon. Sadly the existing platforms at Camden Town are far too narrow to handle such an huge increase in inter-change passenger flows.
Pre-covid the Camden Town cross platform links between branches were close saturation most peak hours which was exacerbated by people lurking at the foot of the surface escallator shaft waiting for the next train destination display to update before stampeding to the relevant platform. There is also the issue of passenger flows in/out the station which at times can be chaotic (think Camden Market) as people to struggle to get to/from escallators on the cross passange to the surface exit.
|
|
|
Post by jimbo on Oct 10, 2020 19:43:00 GMT
20 more trains could provide 30tph service without Camden split, just stabling space, but no improvement south of Kennington. Why not 32tph without split since sub-surface promise that with many flat junctions but Camden is all grade separated. Uplift from current 24tph would be 25%+, a real improvement.
|
|
|
Post by norbitonflyer on Oct 10, 2020 22:34:38 GMT
... I think it is more about junction conflicts at Camden Town since at the current configuration, Charing Cross branch trains will all go to High Barnet/Mill Hill East while Bank branch trains will all go to Edgware without clashing at that junction.... I think you will find the junction at Camden Town already allows the necessary flexibility for trains - look closely at the cutaway diagram here Right now the pointwork at Camden Town Junction could already be set to completely separate the routes into the Mordware and Batternet branches. Camden Town can be set to separate the flows either way, but it is generally supposed that any split would be arranged so each line gets one of the two main depots, which are at Golders Green (on the Edgware branch) and at Morden. This would require Battersea-Edgware and Morden-High Barnet.
|
|
|
Post by quex on Oct 13, 2020 13:14:17 GMT
...it is generally supposed that any split would be arranged so each line gets one of the two main depots, which are at Golders Green (on the Edgware branch) and at Morden. This would require Battersea-Edgware and Morden-High Barnet. Am I right in thinking though that Golders is the "bigger" of the two depots? If so, with the Morden-High Barnet line being the longer, would Morden (along with Highgate Sidings and High Barnet stabling) be able to supply enough trains to run this "line", or would there still need to be some inter-line working to Golders Green?
Either way it's still probably the most logical split - for what it's worth it'll probably be the tidier option on the Tube map too.
|
|
|
Post by Chris L on Oct 13, 2020 15:45:59 GMT
The split requires major works at Camden Town with a new entrance and lifts and escalators as well as cross passage improvements.
The split would also allow a big improvement in the service level on the Battersea extension.
|
|
|
Post by jimbo on Oct 14, 2020 1:22:29 GMT
The current 24tph timetable, available here, says 42 of the 96 trains are provided by Morden depot, and only 17 by the cramped Golders Green depot, which dates back to opening in 1907. Demand currently exceeds the peak service on the Barnet branch, through the Bank branch, and on the Morden branch, so it is this route that is in urgent need of strengthening. Both branches could stable 36tph service needs as required, but 9 trains from Morden are also needed to provide the Charing Cross early morning northbound service until the first trains arrive southbound from Golders Green depot. The Battersea branch would be served by a shuttle to and from Kennington by an overnight stabler there, reversing counter-clockwise around the loop which has now been signalled to allow this. Current plan is for alternate trains to serve Battersea throughout the day, provided from the current fleet by improved maintenance procedures and more efficient running. This will meet opening demand, but as property developments are completed and occupied an improved service would see all Charing Cross trains extended there with additional trains from the Jubilee line released from a new fleet there. With current financial difficulties, perhaps rebuilding Camden Town station will not be possible, but Tube Lines long back suggested 30tph could operate the current service pattern, a 25% service uplift without station reconstruction! I don't see why 33tph wouldn't be possible since the junctions are grade separated, and 32tph is promised on the sub-surface lines with many flat junctions. Camden Town plans would see a new northern ticket hall and escalators to relieve current overcrowded original station entrance. But the deep level interchange subways, essential for a split service, might be constructed separately, using the deep level air raid shelter shaft for access, as was part of original plan for earlier completion.
|
|
|
Post by alpinejohn on Oct 14, 2020 11:40:16 GMT
I seem to recall the original Battersea construction plans showed they were intending to create quite long "over run" tunnels beyond the platforms at Battersea Power Station. Those plans showed the tunnels were far longer than the Battersea platform with the tunnels carefully oriented to allow future extension (seemingly towards Clapham Junction).
Obviously those ancient public plans may have since changed, but it does raise the question of whether at the end of the day a couple of trains could be safely parked overnight in those tunnels to reduce the number of early morning trains which need to be sent up the Charing Cross Branch from Morden?
I have no idea whether track has actually been installed almost through to the end wall or they are simply occupied by a super long sand drag, but from the size of the TBM used, it was obvious the Battersea extension tunnels were super wide compared with earlier Northern Line tunnels, so I guess there should be ample width in those tunnels to install a safe walking route from Batterseas station for drivers to enter/exit any trains parked up overnight. It may require lower approach speed control to Battersea whenever the over-run tunnels are occupied, but as this would be last thing at night it should not impact the final train service levels.
On weekday mornings there is definitely more city branch northbound demand from the south end of the line than for Charing Cross Branch so it must be galling for Morden to have to send quite so many trains up the Charing Cross route first thing every day. Whilst a couple of extra trains may not sound much I suspect it would be well appreciated by the usual sardine hour commuters heading for the city.
|
|
|
Post by Chris L on Oct 14, 2020 12:10:40 GMT
There is an updated Tube map which indicates that the Battersea extension trains would run via Charing Cross. Under the split proposals the service would be joined to the Edgware branch.
|
|
|
Post by jimbo on Oct 14, 2020 18:47:38 GMT
I seem to recall the original Battersea construction plans showed they were intending to create quite long "over run" tunnels beyond the platforms at Battersea Power Station. Those plans showed the tunnels were far longer than the Battersea platform with the tunnels carefully oriented to allow future extension (seemingly towards Clapham Junction). Obviously those ancient public plans may have since changed, but it does raise the question of whether at the end of the day a couple of trains could be safely parked overnight in those tunnels to reduce the number of early morning trains which need to be sent up the Charing Cross Branch from Morden? I have no idea whether track has actually been installed almost through to the end wall or they are simply occupied by a super long sand drag, but from the size of the TBM used, it was obvious the Battersea extension tunnels were super wide compared with earlier Northern Line tunnels, so I guess there should be ample width in those tunnels to install a safe walking route from Batterseas station for drivers to enter/exit any trains parked up overnight. It may require lower approach speed control to Battersea whenever the over-run tunnels are occupied, but as this would be last thing at night it should not impact the final train service levels. On weekday mornings there is definitely more city branch northbound demand from the south end of the line than for Charing Cross Branch so it must be galling for Morden to have to send quite so many trains up the Charing Cross route first thing every day. Whilst a couple of extra trains may not sound much I suspect it would be well appreciated by the usual sardine hour commuters heading for the city. Battersea was designed with two overrun tunnels for stabling defective trains, just like Walthamstow and Brixton. When five extra trains were to be obtained for the extension, three would have stabled overnight there, with only two more sidings required elsewhere. That means one train in each siding and one in a platform. That leaves one platform free because actually they would use the spare position to leave a different place vacant each night, platform or siding, to allow for track cleaning. Now the extra trains have not been obtained, this will not be necessary. To avoid running trains up from Morden to Charing Cross branch early morning, before crowding gets bad, they would have needed very long overrun tunnels, like those for four trains in each beyond Lewisham before the current plan to surface in the Council yard!
|
|
|
Post by xplaistow on Oct 14, 2020 19:00:27 GMT
Just to put some numbers to this, I've done a quick calculation to estimate the number of trains required for a 30-32tph service on both branches (assuming a split). The Edgware-Battersea line would need something like 45-50 trains in service while High Barnet/Mill Hill East-Morden would need more like 70-75.
(If someone else is able to come up with a better estimate, feel free to correct me. This was just a back of envelope calculation.)
|
|
|
Post by jimbo on Oct 14, 2020 19:19:35 GMT
Just to put some numbers to this, I've done a quick calculation to estimate the number of trains required for a 30-32tph service on both branches (assuming a split). The Edgware-Battersea line would need something like 45-50 trains in service while High Barnet/Mill Hill East-Morden would need more like 70-75. (If someone else is able to come up with a better estimate, feel free to correct me. This was just a back of envelope calculation.) Current 24tph service uses 96 of 106 trains. NLU2 was to order 17 more trains for 30tph service. Feasibility study for 36tph split service table said 42 more trains, but subsequently revised in business case to 44 trains (see Aug 2016 Underground News). This would provide 55 for Edgware-Battersea and 77 for Barnet-Morden, remembering that 9 of Edgware branch trains are from Morden depot.
|
|
|
Post by revupminster on Oct 14, 2020 22:07:32 GMT
Northern line not being my expertise and having read all the comments AlpineJohn seems to have the best reasons a split, which has been mooted for as long as I can remember, is unlikely and unworkable
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,758
|
Post by Chris M on Oct 15, 2020 1:03:46 GMT
I don't see the need for a few trains CHX branch trains a day to start from Morden to preclude a split. Obviously the physical connections will remain, and there is precedent for this sort of service on the SSR with District line trains starting from Hammersmith or C&H trains beginning their journey at Upminster. Passengers cope without this being marked on the tube map, but Kennington-Morden could easily be marked as have a limited Edgware line service if desired (either as a dashed line or via a dagger or similar symbol). Obviously this would mean either that Edgware line drivers would need route knowledge from Kennington to Morden or it would need to be worked south of Kennington by a High Barnet line driver. This would require coordination and thought about how to get drivers to the right place at the right time, but these are routine matters for the timetabling department as is so do not preclude a split. A significant upgrade of the interchange capacity at Camden Town is an essential prerequisite of a split (although a split is not a necessary consequence of the upgrade). This was put in black and white in the publicity material about the Camden Town upgrade and is the single biggest reason (and maybe the only reason) why a split has not yet happened despite how long it has been proposed.
|
|
metman
Global Moderator
5056 05/12/1961-23/04/2012 RIP
Posts: 7,421
|
Post by metman on Oct 15, 2020 11:54:08 GMT
From memory the interchange at Euston between the two branches is not great but with HS2 work taking place at Euston could an improved interchange be formed at Euston with passengers being encouraged to change at Euston rather than Camden Town?
|
|
|
Post by johnlinford on Oct 15, 2020 12:20:01 GMT
I can't see a way to do this without significant underground works as the two branches of the northern line are somewhat separated with the City branch having direct change with the Victoria, and the Charring Cross Branch being off to the Northwest and at a different height; customer flow/interchange with the Victoria Line I would imagine is also significant and additional flow from the other branch might overwhelm this?
There are the old tunnels linking them which could be brought back in to use but some of them are now used for ventilation so this would prove complex, they are also fairly narrow and sloped/stepped so not ideal for modern passenger use.
|
|
|
Post by MoreToJack on Oct 15, 2020 14:58:58 GMT
On the topic of 'interworking' in disruption, and early morning/late evening trips to/from depots, I would be surprised if all of these options aren't retained. The precedent is already there with the Circle and Hammersmith & City lines; two 'different' lines to the public but operationally one and the same. Taking a step back from physical trains and crew, the CnH also share service control teams with the Met and District lines - any Northern split would still have the same Controllers and Signallers from Highgate.
Things like route knowledge might become a little harder to retain, but definitely aren't insurmountable problems - again, things the scheduling teams are used to having to deal with, and likewise service control teams having to work around! Reducing day to day operational complexity - even at the expense of slightly more difficult recovery options - is generally a good thing.
|
|
|
Post by jimbo on Oct 15, 2020 19:23:29 GMT
The sub-surface lines have many flat junctions, but there has been no push for the services to be separated in order to achieve 32tph planned with the new signalling. The Northern has grade separated junctions at Camden so beyond 30tph should be achievable. A progressive boost to 33tph would certainly be possible, and quite likely also to 36tph eventually. Current passenger travel plans are well embedded and any split would be disruptive. Camden station rebuilding for heavy interchange with a split service will be unaffordable. Kennington services are generally already separated, apart from the peak boost to Morden line service which would no longer be necessary if the boost continues via the Bank branch to the north. A split service would improve resilience, but at great cost and inconvenience to the travelling public.
|
|
|
Post by 35b on Oct 15, 2020 20:28:06 GMT
The sub-surface lines have many flat junctions, but there has been no push for the services to be separated in order to achieve 32tph planned with the new signalling. The Northern has grade separated junctions at Camden so beyond 30tph should be achievable. A progressive boost to 33tph would certainly be possible, and quite likely also to 36tph eventually. Current passenger travel plans are well embedded and any split would be disruptive. Camden station rebuilding for heavy interchange with a split service will be unaffordable. Kennington services are generally already separated, apart from the peak boost to Morden line service which would no longer be necessary if the boost continues via the Bank branch to the north. A split service would improve resilience, but at great cost and inconvenience to the travelling public. Well said. I remember the threat of similar splits to services on the main line, which all looked fine until I thought about the delights of changing at London Bridge on what had been a through service.
|
|
|
Post by revupminster on Oct 15, 2020 20:48:23 GMT
Will more than 30tph be required on any line post covid?
|
|
|
Post by scheduler on Oct 15, 2020 23:19:15 GMT
Will more than 30tph be required on any line post covid? I hope so .... I hope everything gets back to normal after covid. A grade separated junction is all very well, but it is timetabling the service integrations at Camden Town that are the actual restrictions super-high tph running. That is why the split is proposed, a necessary evil to satisfy the higher density service required Kennington - Morden and Bank branches. I agree it can't (or shouldn't) go ahead until Camden is rebuilt.
|
|
North End
Beneath Newington Causeway
Posts: 1,769
|
Post by North End on Oct 15, 2020 23:45:13 GMT
Will more than 30tph be required on any line post covid? I hope so .... I hope everything gets back to normal after covid. A grade separated junction is all very well, but it is timetabling the service integrations at Camden Town that are the actual restrictions super-high tph running. That is why the split is proposed, a necessary evil to satisfy the higher density service required Kennington - Morden and Bank branches. I agree it can't (or shouldn't) go ahead until Camden is rebuilt. I think more could be timetabled through Camden in theory, but the problem is that it would fall apart in practice when trains don’t present at exactly the right moment, or even worse not in the correct sequence. This then ends up with the junction not performing on the optimum way, which then pushes capacity down. Even now it’s quite important to focus on getting the service in the right order - just one Edgware-Kennington train running around 4 minutes late all day can cause a surprising amount of reactionary delay. Battersea might make this worse as it introduces an extra opportunity for trains to run out of order if some trains still reverse at Kennington. In an ideal world with the current setup we’d have everything go to Battersea with crews stepping back several trains to give scope for righting minor issues.
|
|
|
Post by jimbo on Oct 15, 2020 23:45:22 GMT
Will more than 30tph be required on any line post covid? I hope so .... I hope everything gets back to normal after covid. A grade separated junction is all very well, but it is timetabling the service integrations at Camden Town that are the actual restrictions super-high tph running. That is why the split is proposed, a necessary evil to satisfy the higher density service required Kennington - Morden and Bank branches. I agree it can't (or shouldn't) go ahead until Camden is rebuilt. Ah, but 32tph will be OK for sub-surface over many flat junctions? Then why not at Camden?
|
|
vincenture
Quiz tryhard, and an advocate for simpler, less complicated rail routes
Posts: 885
|
Post by vincenture on Oct 16, 2020 7:30:03 GMT
I think it may be because there isn't a circle line going via camden town round the "city loop" cuz for SSR there's the circle line, and all the sections are shared except junctions. The northern line doesn't have shared sections except the quadruple Camden Town to Euston part. It might not be the actual reason but it may be the case. Also station distances are shorter on average in the central section compared to SSR. But regardless, Camden Town still needs an upgrade. In the meantime, would it be fast enough for trains to reverse at Tooting Broadway as an option to relieve capacity on the Morden section?
|
|