Went past Plumstead Portal today, noticed that there were stockpiles of concrete tunnel segments in the yard, in readiness for tunnelling to commence shortly.
|
|
Ben
fotopic... whats that?
Posts: 4,282
|
Post by Ben on Dec 16, 2012 17:51:48 GMT
Good to see that its progressing.
Does anyone have any thoughts about the revised layout at Abbey Wood? The change from rising between the lines to both being to the north?
|
|
|
Post by crusty54 on Dec 16, 2012 20:10:54 GMT
Good to see that its progressing. Does anyone have any thoughts about the revised layout at Abbey Wood? The change from rising between the lines to both being to the north? This should make an extension eastwards easier.
|
|
Ben
fotopic... whats that?
Posts: 4,282
|
Post by Ben on Dec 17, 2012 0:41:28 GMT
Its interesting you say that. Recently I managed to speak to Terry Morgan after a lecture he gave, and it was his opinion that the new layout was an improvement aswell. I don't understand why though, as it abolishes cross-platform interchange at Abbey Wood, and introduces a flat junction should it be connected to Belvedere?
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Dec 17, 2012 19:54:07 GMT
The revised layout also means that, in the event of Maintenance Works on Crossrail, only one separation barrier need be erected between the Crossrail and Southeastern lines. Using the original alignment would have entailed two separating barriers being erected.
|
|
Ben
fotopic... whats that?
Posts: 4,282
|
Post by Ben on Dec 18, 2012 11:53:30 GMT
Why would that matter?
|
|
|
Post by Jerome H on Dec 19, 2012 20:12:22 GMT
Ben, I don't agree how a terminus such that:
THRU ǀ ǀ BAY BAY ǀ ǀ THRU
is called cross platform interchange, as only half of those who interchange would be able to enjoy the feature. Termini as islands are much more pleasing, unless your bay platforms are staggered back half a train length to create a nice area to move around the platform.
|
|
Chris M
Global Moderator
Forum Quizmaster
Always happy to receive quiz ideas and pictures by email or PM
Posts: 19,758
|
Post by Chris M on Dec 19, 2012 23:46:37 GMT
Not quite half a train length back, but the |#TT#| layout at Dalston Junction seems to be well designed for interchange.
|
|
|
Post by ianvisits on Dec 23, 2012 18:35:07 GMT
Went past Plumstead Portal today, noticed that there were stockpiles of concrete tunnel segments in the yard, in readiness for tunnelling to commence shortly. Some point in the first couple of weeks in January. They don't want to announce a date just yet - just in case it slips due to TBM assembly delays. I had a look around the site last week: www.ianvisits.co.uk/blog/2012/12/19/photos-the-crossrail-tunnel-portal-at-plumstead/
|
|