Hi What is the reason for Bow Church DLR to only be open to 5pm today and tomorrow? kabsonline
|
|
|
Post by alholmes on Mar 4, 2012 8:07:20 GMT
Power supply works - I passed through at about 4:45pm yesterday, just before closure and there were people in the power supply room on the Stratford-bound platform (just beyond the lift) and a generator at street level beside the ticket machines. The lifts weren't working and I suspect the platform lights weren't, either, which might be the reason for the station closure. Also closed before 7am both days.
|
|
|
Post by rsdworker on Mar 4, 2012 13:30:16 GMT
Power supply works - I passed through at about 4:45pm yesterday, just before closure and there were people in the power supply room on the Stratford-bound platform (just beyond the lift) and a generator at street level beside the ticket machines. The lifts weren't working and I suspect the platform lights weren't, either, which might be the reason for the station closure. Also closed before 7am both days. could be problem with power supply but website didn't mention about lifts being out of order during works
|
|
|
Post by pib on Mar 19, 2012 16:35:48 GMT
FYI the work undertaken was the replacement of the LV switchgear.
|
|