Post by flippyff on Apr 8, 2010 21:23:51 GMT
ted.europa.eu/udl?uri=TED:NOTICE:100168-2010:TEXT:EN:HTML&src=0
HTIOI
Simon
"
Title attributed to the contract by the contracting entity
East London line phase 2 - civil engineering and permanent way works.
Short description of the contract or purchase(s)
The construction of an extension of the East London Line from a junction south of Surrey Quays Station through c.1.3km of new constructed railway to a junction north of Queens Road Peckham Station on Network Rail's South London Line Railway. Further details are given in the Pre-qualification Briefing Document available at tfl.bravosolution.co.uk.
Total quantity or scope
The proposed East London Line Phase 2 Civil Engineering and Permanent Way contract will consist of the construction of a new c.1.3km railway (the Silwood Lines) following a disused alignment up to defined boundaries with Network Rail and provide provision for future construction of a new station adjacent to Surrey Canal Road. The construction of a new station at Surrey Canal Road may be provided for as an option within any contract arising out of this Contract Notice. Further details of the requirment are given in the Pre-qualification Briefing Document available at tfl.bravosolution.co.uk.
Options
Yes
description of these options: The construction of a new station at Surrey Canal Road.
DURATION OF THE CONTRACT OR TIME LIMIT FOR COMPLETION
Starting 29.10.2010 Completion 14.9.2011 "
Title attributed to the contract by the contracting entity
East London line phase 2 - civil engineering and permanent way works.
Short description of the contract or purchase(s)
The construction of an extension of the East London Line from a junction south of Surrey Quays Station through c.1.3km of new constructed railway to a junction north of Queens Road Peckham Station on Network Rail's South London Line Railway. Further details are given in the Pre-qualification Briefing Document available at tfl.bravosolution.co.uk.
Total quantity or scope
The proposed East London Line Phase 2 Civil Engineering and Permanent Way contract will consist of the construction of a new c.1.3km railway (the Silwood Lines) following a disused alignment up to defined boundaries with Network Rail and provide provision for future construction of a new station adjacent to Surrey Canal Road. The construction of a new station at Surrey Canal Road may be provided for as an option within any contract arising out of this Contract Notice. Further details of the requirment are given in the Pre-qualification Briefing Document available at tfl.bravosolution.co.uk.
Options
Yes
description of these options: The construction of a new station at Surrey Canal Road.
DURATION OF THE CONTRACT OR TIME LIMIT FOR COMPLETION
Starting 29.10.2010 Completion 14.9.2011 "