Post by seaeagle on Sept 30, 2011 10:33:37 GMT
Is the distance to go new signaling system in operation on some parts of the victoria line yet? The asset replacement signaling is in operation between walthamstow and Finsbury Park.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Sept 30, 2011 12:46:35 GMT
The last two trains, new trains 1 and 2 are expected in November I believe. Train 1 around 21st and Train 2 around end of the month.
|
|
SE13
In memoriam
RIP 23-Oct-2013
Glorious Gooner
Posts: 9,737
|
Post by SE13 on Sept 30, 2011 13:26:58 GMT
The last two trains, new trains 1 and 2 are expected in November I believe. Train 1 around 21st and Train 2 around end of the month. I'm getting a touch lost now - What numbers will these have?
|
|
|
Post by seaeagle on Sept 30, 2011 13:31:42 GMT
The last two trains, new trains 1 and 2 are expected in November I believe. Train 1 around 21st and Train 2 around end of the month. I'm getting a touch lost now - What numbers will these have? The offical communications that I get at work have them down as T1/48 & T2/49!!! Any clearer. lol
|
|
SE13
In memoriam
RIP 23-Oct-2013
Glorious Gooner
Posts: 9,737
|
Post by SE13 on Sept 30, 2011 21:22:39 GMT
I'm getting a touch lost now - What numbers will these have? The offical communications that I get at work have them down as T1/48 & T2/49!!! Any clearer. lol Ok, I'll wait and see!
|
|
|
Post by 100andthirty on Oct 1, 2011 9:01:13 GMT
I hope this is absolutely clear:
they are being built as the 48th and 49th trains, but they will be numbered and recorded on all LU systems as trains 1 and 2.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Oct 3, 2011 18:19:18 GMT
I hope this is absolutely clear: they are being built as the 48th and 49th trains, but they will be numbered and recorded on all LU systems as trains 1 and 2. They are, which is why I wrote new train 1 and new train 2! The A Cars will be numbered 11001, 11002, 11003 and 11004.
|
|
SE13
In memoriam
RIP 23-Oct-2013
Glorious Gooner
Posts: 9,737
|
Post by SE13 on Oct 3, 2011 19:37:25 GMT
SE13 syndrome, don't worry, the expression is about to explode over this place. ;D
|
|
|
Post by seaeagle on Oct 7, 2011 13:54:06 GMT
Last two cars of T47 arrived at the depot on Tuesday morning. T1 has been built at Derby but is going to be delayed by a lack of doors. Next batch of doors is due to be delivered to Derby on 24th october, by which time T2 should be complete minus it's doors.
|
|
|
Post by malcolmffc on Oct 18, 2011 23:29:06 GMT
So is T47 in service?
|
|
|
Post by seaeagle on Oct 19, 2011 7:46:46 GMT
Not as yet, was still on 39 road being tested yesterday. Will post as soon as I know an expected date to enter service if I can, (I'm on leave next week .
|
|
|
Post by seaeagle on Oct 19, 2011 10:08:12 GMT
Not as yet, was still on 39 road being tested yesterday. Will post as soon as I know an expected date to enter service if I can, (I'm on leave next week . Just been informed that T47 should have it's commissioning run this coming Friday, so if it passes, will be available for service after that. Bear in mind that there the Vic is shutdown this weekend.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Oct 19, 2011 15:58:39 GMT
Not as yet, was still on 39 road being tested yesterday. Will post as soon as I know an expected date to enter service if I can, (I'm on leave next week . Just been informed that T47 should have it's commissioning run this coming Friday, so if it passes, will be available for service after that. Bear in mind that there the Vic is shutdown this weekend. That is my understanding too. I'll try and remember to post when it enters service if nobody else gets round to it first, being as seaeagle is on holiday.
|
|
|
Post by seaeagle on Oct 21, 2011 15:55:52 GMT
Just been informed that T47 should have it's commissioning run this coming Friday, so if it passes, will be available for service after that. Bear in mind that there the Vic is shutdown this weekend. That is my understanding too. I'll try and remember to post when it enters service if nobody else gets round to it first, being as seaeagle is on holiday. Train 47's commissioning run ended up shutting the whole line down! I don't know where it failed, but the problem was no ATO or ATP available and caused an 18 minute delay at 14.47. Delivery dates for T1 is 30th Nov and T2 16th dec.
|
|
|
Post by superteacher on Oct 27, 2011 21:17:56 GMT
So T47 is on the naughty chair then! Or has it been let into service now?
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Oct 27, 2011 21:38:19 GMT
On the naughty chair in the naughty corner at the moment!
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Oct 28, 2011 10:06:28 GMT
It is ready to go in service pretty much, it is just being used for other things at the moment.
|
|
|
Post by seaeagle on Nov 5, 2011 10:06:33 GMT
Here's something different, an 09 going the other way! In the last few days train 20 has been decommissioned and has been taken back to Derby, reason unknown to me at this time as I've been on leave.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 5, 2011 10:13:37 GMT
Here's something different, an 09 going the other way! In the last few days train 20 has been decommissioned and has been taken back to Derby, reason unknown to me at this time as I've been on leave. Oh no, that doesn't sound good, it must be sufficiently serious to merit sending the whole train back, right?
|
|
|
Post by seaeagle on Nov 5, 2011 11:11:28 GMT
Here's something different, an 09 going the other way! In the last few days train 20 has been decommissioned and has been taken back to Derby, reason unknown to me at this time as I've been on leave. Oh no, that doesn't sound good, it must be sufficiently serious to merit sending the whole train back, right? It appears T20 had an issue with sluggish movement on Sat 29th Oct and was withdrawn from service, but I wouldn't of thought that it would need a trip to Derby for that, I can only assume that something else showed up when the train returned to depot for examination into the defect.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 5, 2011 22:45:36 GMT
Not that serious, one or some of the cars are built with bodyside panels in the wrong place, so it is going back to have those cars put right so that the emergency access cocks are in the same place as all of the other trains!
Nothing to do with sluggish movement, but an issue that has been there since it was built, LU just wanted it sorting out!
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 7, 2011 11:32:11 GMT
T47 is in service today.
|
|
|
Post by seaeagle on Nov 9, 2011 13:26:16 GMT
It didn't last long, failed again on it's first day in service with an ATO problem again.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 9, 2011 13:40:21 GMT
Perhaps it should have stayed on the naughty chair in the naughty corner then ;D ;D ;D
|
|
Ben
fotopic... whats that?
Posts: 4,282
|
Post by Ben on Nov 9, 2011 15:55:30 GMT
By and large, has the fleet started to settle in yet? Are they showing more potential than the S stock? Are they generally liked by people working with them now?
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 9, 2011 16:43:00 GMT
It didn't last long, failed again on it's first day in service with an ATO problem again. It did, hope its not done the same again today else it might be getting condemned!!
|
|
|
Post by seaeagle on Nov 9, 2011 19:06:52 GMT
Over the weekend the D-car of the new train 1 was damaged in an incident when the train was being moved. In order to keep to delivery dates, the new train 2's D-car will be used to replace the one in train 1. I assume that the D-car will be renumbered into train 1's number sequence.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Nov 9, 2011 19:51:18 GMT
Ooops ;D
|
|
|
Post by seaeagle on Nov 30, 2011 15:31:43 GMT
First two cars of Train 1 arrived at the depot yesterday, (Tuesday), delivery of the other six cars should be completed by Tuesday 6th december.
|
|
|
Post by seaeagle on Dec 1, 2011 21:43:21 GMT
First two cars of Train 1 arrived at the depot yesterday, (Tuesday), delivery of the other six cars should be completed by Tuesday 6th december. Next two cars in the depot, two more due for next Monday and last two for next Tuesday.
|
|