|
Post by norbitonflyer on Nov 5, 2015 0:17:55 GMT
Mod Comment: Use this thread to discuss the merits of DC vs AC electrification.and my point is that you (hopefully!) only build things once, but passengers have to use it for the next 100 years, amortising the additional costs rather well. ! Indeed so, but as Phil pointed out, having ohle and live rail on adjacent tracks is a headache long after construction is finished, both for the signalling engineers and for any maintenance that needs doing Also, hopefully that DC electrification will all be OHLE within the next 25-50 years. ! I very much doubt it: the existing DC network mileage is far more extensive than the entire mileage that has been electrified on AC in the past fifty years, and electrifying non-electrified lines is a much higher priority than converting from one system to another. The DC system works - most of the time. Yes ice is a problem but at least the conductor rails tend to stay where they are and don't get blown away in high winds or mangled by errant current collection equipment you then would actually then have enough surface platforms for the slows and CR2 if you were to also evict Thameslink. I think you mean Tramlink - or you will have some explaining to do to the residents of Haydons Road and Tooting Junction!
|
|
|
Post by stapler on Nov 5, 2015 8:04:27 GMT
Doubt whether we'll see the any of 3rd rail any time soon, but pause for reflection-- the LBSCR was right!
|
|
|
Post by norbitonflyer on Nov 5, 2015 10:20:00 GMT
Even with a 20/20 hindsight mirror, and 100 years later, that's debatable. The LSWR electrified its system much faster than the LBSCR. By the time of the grouping the wires had only reached Crystal Palace, but the live rails had got to Shepperton, Hampton Court and Claygate. Even by 1925 the wires had only reached Coulsdon and Sutton. At that rate, it is most unlikely electric trains would have reached the south coast by 1939, let alone 1932. And given the glacial pace of electrification since 1948, it is quite likely that most of the former Southern Region would still be diesel hauled now - or, more likely, would have suffered the fate of most lines in the south that had not been electrified by the time the Doctor prescribed major surgery to the network.
|
|
|
Post by stapler on Nov 5, 2015 12:38:48 GMT
Surely the OHE would have developed under the New Works and unemployment relief measures just as the third rail did?
|
|
|
Post by domh245 on Nov 5, 2015 13:51:40 GMT
It's worth noting that Network Rail's policy now is that when DC equipment comes round for renewal, where possible they will try to start converting, or at the very least doing the basework for conversion to AC OHLE. General feeling is that the BML would be the most sensible option to convert first, because before long, a large amount of the stock working it will be Dual Voltage. There is also a policy of no more third rail installations wherever possible, you can expect lines like Uckfield and Marshlink to be electrified at about the same time that the rest of the network is.
|
|
|
Post by norbitonflyer on Nov 5, 2015 13:58:01 GMT
The new Works scheme was a London Transport initiative, involving replacement of trams by trolleybuses and extension of the Central and Northern Lines over tracks of the GWR and LNER. The Railways (Agreement) Act, 1935 supported some projects under the unemployment relief programme, but electric trains had already reached the south coast by then (as far as Worthing in the west and Hastings in the east. The Portsmouth electrification (three routes, from Worthing, Sutton and Surbiton) was the only Southern Railway project which benefitted from the funding.
|
|
|
Post by tjw on Nov 5, 2015 16:28:09 GMT
Even with a 20/20 hindsight mirror, and 100 years later, that's debatable. The LSWR electrified its system much faster than the LBSCR. By the time of the grouping the wires had only reached Crystal Palace, but the live rails had got to Shepperton, Hampton Court and Claygate. Even by 1925 the wires had only reached Coulsdon and Sutton. At that rate, it is most unlikely electric trains would have reached the south coast by 1939, let alone 1932. And given the glacial pace of electrification since 1948, it is quite likely that most of the former Southern Region would still be diesel hauled now - or, more likely, would have suffered the fate of most lines in the south that had not been electrified by the time the Doctor prescribed major surgery to the network. The LB&SCR was not entirely right they chose 6.6 kV AC supply. The other problem with this system was that it came from Allgemeine Elektricitäts Gesellschaft of Berlin, which was a bit of a problem when the Government decided to go to war with Germany! I believe this system requires fewer transformers, and so would be quicker and easier to install once a British company would be found to deliver the electrical equipment.
|
|
rincew1nd
Administrator
Junior Under-wizzard of quiz
Posts: 10,286
Member is Online
|
Post by rincew1nd on Nov 5, 2015 16:50:24 GMT
There is also a policy of no more third rail installations wherever possible... Quite, as a consequence MerseyRail is looking at procuring dual-voltage units to replace the 507/508 fleet to allow future electrification from Bidston to Wrexham as well as the various other works on the horizon. I can't see why anyone would procure new stock that doesn't at least have some kind of passive provision for overhead electrification.
|
|
|
Post by norbitonflyer on Nov 5, 2015 17:03:09 GMT
I believe this system requires fewer transformers, and so would be quicker and easier to install once a British company would be found to deliver the electrical equipment. [/span] [/quote] Smaller transformers, maybe, but you would still need one on board, as 6,600V is still a lot to design traction equipment for. And in any case it needs to be rectified to dc first - even if you use modern variable-ac motors you need to remove the supply frequency. A DC traction supply puts all the heavy and sensitive equipment on shore, so to speak, instead of lugging it around and shaking it about on board. The problem is that you can't send low voltage DC very far, so you need a lot more substations to cover an area. That is why DC is preferred for operations with a lot of trains in a small area, and ac for fewer trains spread over a wider area. I can't see why anyone would procure new stock that doesn't at least have some kind of passive provision for overhead electrification. I can't see the deep tubes ever needing it, and space it as a premium thee anyway, but I don't think anyone in the UK other than LUL has not specified such passive provision since at least the Class 465s, which are now over twenty years old.
|
|
|
Post by domh245 on Nov 5, 2015 17:13:41 GMT
I can't see why anyone would procure new stock that doesn't at least have some kind of passive provision for overhead electrification. I can't see the deep tubes ever needing it, and space it as a premium thee anyway, but I don't think anyone in the UK other than LUL has not specified such passive provision since at least the Class 465s, which are now over twenty years old. You forgot the 460s. Whilst they could in theory operate in AC, much like their sister units at SWT, they didn't have pantograph wells built into the bodyshell, so any modification to fit AC would have meant an expensive bodge-job or new vehicles. However, it's all academic now because they have become 458/5s, although the few fully ex-460 units don't have any pantograph wells, so it seems likely that they for one certainly won't be going over to AC.
|
|
|
Post by stapler on Nov 5, 2015 19:13:01 GMT
NF, the LNER realised that the short distance Shenfield electrification and widening would be better done with 1500v DC OHE than third rail, even though the LMS had electrified its suburban lines to Upminster without overhead. And of course, the LNE was also handing over the Loughton/Fairlop lines to LT DC. By the 30s the SR surely knew it was extending an already outmoded and less advanced system, especially on lines such as the Portsmouth direct.
|
|
|
Post by mrjrt on Nov 6, 2015 1:12:23 GMT
I very much doubt it: the existing DC network mileage is far more extensive than the entire mileage that has been electrified on AC in the past fifty years, and electrifying non-electrified lines is a much higher priority than converting from one system to another. All equipment has a use-by date. If it's cheaper to replace like-for-like then they will. If it's cheaper to convert it, then they will. 3rd rail is non-standard, and that equipment will need to be produced somewhere. The costs came in that Southampton to Basingstoke like-for-like renewals would cost more than converting to OHLE, so that is what is planned. Additonal network costs will be factored in - if the substations around Clapham Junction were to reach expiry next, then I doubt Clapham Junction to Waterloo and Victoria would be up for conversion, but if say the BML south of Haywards Heath were to need major DC renewals, I suspect we would see OHLE put in place instead. You might even see equipment moved - taking the DC equipment from more recent renewals across the network to extend the life of the DC infrastructure in London could well happen. The intended plan after Southampton to Basingstoke was (last I saw), to convert the North Kent lines east of Fareham so that South Eastern's HS1 services would only require OHLE, OHLE to Ore for HS1 services via Ashford, and the conversion of the Oxted lines to South Croydon from DC and Diesel to OHLE. I suspect the BML south of Croydon would probably feature after those. I think you mean Tramlink - or you will have some explaining to do to the residents of Haydons Road and Tooting Junction! Nope, Tramlink's being evicted regardless.
|
|
|
Post by phil on Nov 7, 2015 13:04:18 GMT
Even with a 20/20 hindsight mirror, and 100 years later, that's debatable. The LSWR electrified its system much faster than the LBSCR. By the time of the grouping the wires had only reached Crystal Palace, but the live rails had got to Shepperton, Hampton Court and Claygate. Even by 1925 the wires had only reached Coulsdon and Sutton. At that rate, it is most unlikely electric trains would have reached the south coast by 1939, let alone 1932. And given the glacial pace of electrification since 1948, it is quite likely that most of the former Southern Region would still be diesel hauled now - or, more likely, would have suffered the fate of most lines in the south that had not been electrified by the time the Doctor prescribed major surgery to the network. The LB&SCR was not entirely right they chose 6.6 kV AC supply. The other problem with this system was that it came from Allgemeine Elektricitäts Gesellschaft of Berlin, which was a bit of a problem when the Government decided to go to war with Germany! I believe this system requires fewer transformers, and so would be quicker and easier to install once a British company would be found to deliver the electrical equipment.It is not the voltage that is an issue (6.25KV AC was used by BR in the 60s as a way of minimising the amount of bridge works on some newly electrified lines), its frequency. The German system of electrification uses a low frequency of 16.75Hz because it was discovered very early on that DC traction motors would work with this power source*. The LBSCR latched onto this because it made long distance AC electrification viable - while it was readily understood that AC transmission was far more efficient - the only way of converting it was large rotary converters (i.e. turning AC into mechanical movement then generating DC) which wouldn't fit into a train. Hence everyone else (most of whom were only interested in urban electrification to compete with trams) going for DC based schemes which required less expensive electrical equipment that could be sourced from the UK. Yes by the 30s the Southern could have invested in 1500VDC Overheads - but this introduces more complications in having two separate systems to look after. Given the Southern was a private company with shareholders to answer too, introducing a totally new electrification system requiring trains fitted with equipment to cope with both, when the 3rd rail schemes had proved to be very cost effective to date was not going happen. It took until the late 1950s and the introduction of Mercury Arc rectifiers before AC - DC conversion could be undertaken on the train itself. As things stand the German system, while being AC is far from perfect due to its use of a non standard frequency - lines built in the past few decades are at 25KV AC @ 50Hz for this very reason, with most traction built in recent years being similarly equipped. However as with our DC network, the cost of conversion and resulting disruption outweighs the benifits *AC traction motors are difficult beasts to control and they have only become a realistic option thanks to computer control in the past few decades.
|
|
|
Post by stapler on Nov 8, 2015 8:22:02 GMT
I always thought it was the Clapton tunnels that made BR go for 6250v AC on the Chenfords, not bridges? Or is this just the other side of the same coin?
|
|
|
Post by phil on Nov 8, 2015 13:08:50 GMT
I always thought it was the Clapton tunnels that made BR go for 6250v AC on the Chenfords, not bridges? Or is this just the other side of the same coin? Same principle and reasoning be it bridge or tunnel though. In the event later research allowed the clearances to be reduced - put it this way there is no way the Thameslink tunnels under London (even with their lowered trackbeds) would be considered suitable for 25KV in the early 1960s - yet by the early 80s such clearances were considered fine for 25KV.
|
|
|
Post by norbitonflyer on Nov 8, 2015 14:00:08 GMT
The German system of electrification [used by the LBSCR and the Midland] uses a low frequency of 16.75Hz because it was discovered very early on that DC traction motors would work with this power source*. David Brown's book on the Southern Electric says of the South London sets (I assume the later designs were the same as he doesn't mention any differences) that the voltage was stepped down on board, four "taps" off the transformer making power available to the motors at four different voltages - rather like cutting in resistors on a dc train, but without the excess heat. As he doesn't mention rectifiers I assume the motor supply was at ac. I was puxxled as to how an electric motor supplied with current alternating at 16.75 Hz (or indeed any other frequency) can run at any rotation speed other than that of the supply frequency (1005rpm), but on looking it up I see that the trick is to supply ac to both the rotor and stator (i.e neither of them is a permanent magnet) so the two switch polarity in unison. Incidentally, are you sure it's 16.75 Hz? Most sources say 16.67 which is not only is it exactly one third of the standard 50Hz, and thus easy to generate from a three phase supply, but it is exactly 1000rpm. NF, the LNER realised that the short distance Shenfield electrification and widening would be better done with 1500v DC OHE than third rail, even though the LMS had electrified its suburban lines to Upminster without overhead. the Upminster route was electrified on the live rail system because the trains that were to use it had to run through to the District Line. as for the LNER, it and one of its predecessors had been using the 1500V dc OHLE system since 1915. I always thought it was the Clapton tunnels that made BR go for 6250v AC on the Chenfords, not bridges? It was to avoid the need for increasing clearances on the Shenfield line, which already had ohle at 1500dc, when it was converted to ac. I'm not even sure if the Chingford line was initially electrified at the lower (6250) voltage.
|
|
|
Post by stapler on Nov 8, 2015 16:04:10 GMT
Chingford/Enfield definitely was 6250v for about 20 years. Don't remember any bridges being raised on conversion. Some of the masts on Shenfield are still the 1949 ones. Big programme currently to replace.
|
|
|
Post by phil on Nov 11, 2015 20:43:56 GMT
I very much doubt it: the existing DC network mileage is far more extensive than the entire mileage that has been electrified on AC in the past fifty years, and electrifying non-electrified lines is a much higher priority than converting from one system to another. All equipment has a use-by date. If it's cheaper to replace like-for-like then they will. If it's cheaper to convert it, then they will. 3rd rail is non-standard, and that equipment will need to be produced somewhere. The costs came in that Southampton to Basingstoke like-for-like renewals would cost more than converting to OHLE, so that is what is planned. Additonal network costs will be factored in - if the substations around Clapham Junction were to reach expiry next, then I doubt Clapham Junction to Waterloo and Victoria would be up for conversion, but if say the BML south of Haywards Heath were to need major DC renewals, I suspect we would see OHLE put in place instead. You might even see equipment moved - taking the DC equipment from more recent renewals across the network to extend the life of the DC infrastructure in London could well happen. The intended plan after Southampton to Basingstoke was (last I saw), to convert the North Kent lines east of Fareham so that South Eastern's HS1 services would only require OHLE, OHLE to Ore for HS1 services via Ashford, and the conversion of the Oxted lines to South Croydon from DC and Diesel to OHLE. I suspect the BML south of Croydon would probably feature after those. As you say, its not just the electrification kit that you have to consider... With regard to the South Western main line beyond Basingstoke its easy - all electric SWT services are operated by Desiros which only require a pantograph and 25KV transformer fitting (plus a few minor mods) to convert them to dual voltage. Inwards of Basingstoke you start to encounter 455s which are not cheap or easy to convert. Yes the new traction package might be suitable, but the bodyshells were not built for AC conversion in mind plus none of the necessary cabling is there. As a result replacing like for like suddenly looks a lot better than conversion plus a new fleet of trains... The BML is similary easy with regards to outer services (which use Electrostars / Thameslink units) - but runs into problems north of Redhill where 455s start to appear. On SE, it is the Networkers that are an issue - although they are newer than the 455s, they were never built with conversion to AC in mind. Again once you get towards the coast where everything is a Electrostar or a Javalin its not such a problem.
|
|
|
Post by norbitonflyer on Nov 11, 2015 21:37:31 GMT
Inwards of Basingstoke you start to encounter 455s which are not cheap or easy to convert. Yes the new traction package might be suitable, but the bodyshells were not built for AC conversion in mind Don't be misled by the ac traction package - everything from Networkers on have had ac traction motors, but the traction system still needs a dc supply - even if the external supply is ac you still need to convert from 50Hz to 0Hz (dc) and back again to variable ac. It might be possible to convert the 455s - the 317s and 318s are very similar in most respects except for the presence of a pantograph and transformer. The 465s appear to be very similar to the 365s, which certainly can work on both ac and dc. Anyway - the 455s won't last for ever - they are already over 30 years old.
|
|
|
Post by phil on Nov 11, 2015 22:40:22 GMT
Inwards of Basingstoke you start to encounter 455s which are not cheap or easy to convert. Yes the new traction package might be suitable, but the bodyshells were not built for AC conversion in mind Don't be misled by the ac traction package - everything from Networkers on have had ac traction motors, but the traction system still needs a dc supply - even if the external supply is ac you still need to convert from 50Hz to 0Hz (dc) and back again to variable ac. It might be possible to convert the 455s - the 317s and 318s are very similar in most respects except for the presence of a pantograph and transformer. The 465s appear to be very similar to the 365s, which certainly can work on both ac and dc. Anyway - the 455s won't last for ever - they are already over 30 years old. Regarding the 455s - they might be 30 years old but if the leasing company feels its worth fitting them with a brand new traction package then it must think they will be around for quite a while yet - fitting a new traction package isn't cheap! Thing is if they are re-powered, their longevity will then become a case of for how long can the bodyshells be kept going? As for fitting them with AC kit - it all depends on the bodyshell. Just beause the 317s, etc are of the same visual design, it doesn't automatically mean the 455s bodyshell is quick or easy to modify at this late stage in their careers. Turning to the 365 / 465s you need to consider their history. The 465s were designed and ordered by NSE well before anyone had any thoughts of converting 3rd rail to overheads and they were expected to continue trundling around the SE division for the next 40 years just as their slam door predecessors had done. The 365s were ordered 5 years later by the Government to try and tide the York works over in the run up to Privatisation so it was decided to give them the flexibility to be deployed both the GN and SE sections. While they look similar from the outside, the truth is there is not much else that is the same between the two. The 365s simply used the Networker bodyshell to kept the costs down and as such the internals are very different between the two classes - the 465s do not have any passive provision for conversion to 25KV (as is standard for 3rd rail EMUs built today) so they would require a through rebuild to become dual voltage units.
|
|
|
Post by spsmiler on Nov 12, 2015 9:37:54 GMT
Maybe the way to convert 465s to dual voltage is to build extra coaches which have the pantographs and other control gear?
Simon
|
|
|
Post by stapler on Nov 12, 2015 9:54:40 GMT
Yes, phil - but weren't the tracks under the Clapton tunnel lowered about then, too? I remember a long closure... Did the nature of electricity change during those 20 years, I wonder?!
|
|
|
Post by norbitonflyer on Nov 12, 2015 10:10:55 GMT
Maybe the way to convert 465s to dual voltage is to build extra coaches which have the pantographs and other control gear?Simon Likewise the 455s, a possible way of creating ten car trains in both cases (althoiugh SE want to go to twelve which is not so easy, and already makes the future of the five-car 376s uncertain). Any such augmentation would, of course, require extra power (maybe a third power bogie under one of the cars?), and result in units in which one car was very much newer than the rest. This is by no means unheard of on the Southern (indeed the class 455/7s already include one vehicle older than the rest, and the immediate post war period saw many original 3SUBs augmented with a post-war all-steel trailer - see also the Q stock, "58 trailers" and the 1960 stock for LU examples) , but it does leave a problem that the new cars will not have a long life before the rest of the unit is life expired. All in all, the re-engineering is unlikely to cost much less than building new units - certainly when whole life costs are taken into account. And as SWT is rediscovering at the moment with its 458s, you can't re-engineer your existing fleet without taking it out of service first, whereas with a new fleet you can maintain the service with the old trains until the new ones are ready. This is a lesson they should have learned from the old Southern Region, which had the same problem when building the 442s, using equipment recovered from the REPs.
|
|
|
Post by norbitonflyer on Nov 12, 2015 10:20:00 GMT
Did the nature of electricity change during those 20 years, I wonder?! Maybe at the time of conversion they erred on the side of caution, but later experience revealed that narrower clearances worked. Remember also that when the electrification first took place, the railway environment was rather different, in that on many lines it was still a common occurrence for large clouds of water vapour and soot (essentially carbon - an electrical conductor) to be showered on anything above the centre line of the track - not to mention the metal protrusion these emissions emanated from - so flashovers may have been more likely. I do recall reading that tracks were lowered in some places on the Shenfield line, and this has led to problems with provision of step-free access on Crossrail as platform heights on the GEML are consequently somewhat higher (relative to the train) than they are on the GWML.
|
|
|
Post by stapler on Nov 12, 2015 12:11:04 GMT
NF, you are probably right. I remember a BR manager talking about soot deposits (from generations of N7s and B17s) in those tunnels being an inch or so thick!
|
|
|
Post by brigham on Nov 12, 2015 13:29:27 GMT
I was expecting to see discussion on the relative merits of DC/AC traction. This topic is all about conductor systems.
|
|
|
Post by norbitonflyer on Nov 12, 2015 13:58:28 GMT
brighamThe thread opened with "discuss the merits of DC vs AC electrification". Certainly the supply to the traction motor type is a factor, although not as much as you might think except for the rather unusual systems initially used by the Brighton and the Midland. Indeed, until rectifiers suitable for onboard use were available in the 1950s, delivery to the train was normal, and the main debate was between overhead (as used by the LNER) and live rail (as used by everyone, including the LNER on Tyneside).
|
|
|
Post by A60stock on Nov 12, 2015 14:06:43 GMT
regarding the class 455 with SWT:
Are there any in service with the new traction package, and if not when will they start entering service?
|
|
|
Post by domh245 on Nov 12, 2015 15:04:33 GMT
As far as I am aware, 2 have been converted, and are currently doing mileage accumulation. None in service yet.
|
|
|
Post by norbitonflyer on Nov 12, 2015 15:09:06 GMT
regarding the class 455 with SWT: Are there any in service with the new traction package, and if not when will they start entering service? This article suggests the first was to have entered service in July this year, with all treated by next August. However, there is little externally to tell them apart - the quite separate internal refurbishment programme is rather more obvious (noisier hustle alarms being the most noticeable change there) - so I don't know whether that was achieved. Certainly SWT, usually not backward in blowing their own trumpet, do not seem to have issued any press release or information on their website.
|
|