Post by jardine01 on Jun 2, 2011 8:48:47 GMT
Hi everyone, does anybody know why the Jubilee line is fully closed this weekend according to Transport for London? Normally its West Hamstead to Stanmore closed isent it?
|
|
|
Post by version3point1 on Jun 2, 2011 12:33:51 GMT
Saturday is a normal service. It's only suspended on Sunday until 0815, after which the suspension is between West Hampstead and Stanmore until 2130, and then extended Waterloo to Stanmore after 2130 until the close of traffic.
The original West Hampstead to Stanmore closure for this Sunday was supposed to be for trial ops, so one can only assume they want to run trial ops in ATO on the whole of the line a short period of time.
|
|
|
Post by Tubeboy on Jun 2, 2011 14:00:52 GMT
From what I read, trains will be in ATO Stratford to West Hampstead, then detraining and running in ATO up to Stanmore, and not reversing via the siding. Be the same when returning South/East.
|
|
DWS
every second count's
Posts: 2,487
|
Post by DWS on Jun 8, 2011 11:40:21 GMT
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 8, 2011 11:44:06 GMT
We must be nearly there.
|
|
|
Post by jardine01 on Jun 8, 2011 13:32:47 GMT
How Many more closures is there until Dollis Hill to Stanmore goes ATO?
|
|
|
Post by Dstock7080 on Jun 8, 2011 14:13:04 GMT
How Many more closures is there until Dollis Hill to Stanmore goes ATO? 25/26 June: Jubilee Line No service between West Hampstead and Stanmore. (Trains will operate empty between West Hampstead and Stanmore for Trial Operations on Sunday.) Sunday 3 July: Jubilee Line Neasden Depot Re-Signalling No service between Stanmore and Willesden Green. (Reduced services Willesden Green - Stratford.) New timetable (WTT11) from Sunday 31 July. Running time has been revised to reflect operation with the new TBTC signal control system. Platform 3 has been commissioned at Stanmore and is utilised throughout the week.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 11, 2011 16:40:44 GMT
So maybe June 27th for ATO and TBTC on the whole line with WTT10 then?
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 11, 2011 17:07:23 GMT
Trail ops Not on this weekend due to the fact it went so well last weekend. Should be all up and running TBTC with WTT11 July. If all goes ok.
|
|
|
Post by Dstock7080 on Jun 17, 2011 14:39:51 GMT
"From Sunday 26 June the whole of the Jubilee line will be commissioned to be under the control of the TBTC system and the whole line will be running in ATO. It is anticipated that trains will commence operation in passenger service between Stanmore and West Hampstead at some point during the day following the completion of trial operations." !!
|
|
|
Post by malcolmffc on Jun 17, 2011 18:57:36 GMT
Fantastic news!
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 17, 2011 22:09:46 GMT
The latest Planned works calendar shows closures between Stanmore and Willesden Green on 3, 23-24 July and 3-4 September. Are they all for Neasden resignalling? Given that the resignalling programme is supposed to be finally completed next weekend, all these additional closures seem unfortunate.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 18, 2011 6:12:16 GMT
|
|
|
Post by Dstock7080 on Jun 18, 2011 10:48:03 GMT
The latest Planned works calendar shows closures between Stanmore and Willesden Green on 3, 23-24 July and 3-4 September. Are they all for Neasden resignalling? Given that the resignalling programme is supposed to be finally completed next weekend, all these additional closures seem unfortunate. Nothing planned for 23/24 July. Other closures are for Neasden resignalling work.
|
|
|
Post by uzairjubilee on Jun 18, 2011 11:43:37 GMT
Yay.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jun 25, 2011 7:59:35 GMT
"From Sunday 26 June the whole of the Jubilee line will be commissioned to be under the control of the TBTC system and the whole line will be running in ATO. It is anticipated that trains will commence operation in passenger service between Stanmore and West Hampstead at some point during the day following the completion of trial operations." !! Target is 1200 for whole line passenger service .... not being advertised as such just in case.
|
|
|
Post by Tubeboy on Jun 25, 2011 15:13:06 GMT
The work on the 3rd July is Neasden depot resignalling. Other dates I assume are for track replacement or drainage works or summat similar.
|
|