Quite a bit of major work coming up on the District.
27th,28th January, track replacement work at Monument,no service Whitechapel-Earl's Ct. 24th,25th February,bridge work at Chiswick Pk,no service Turnham Grn-Acton-Town(District only). 2nd to 9th March,bay road OOC Tower Hill(trains reversing Mansion House) 3rd,4th March,drainage work at Gloucester Rd,no service Whitechapel-Earl's Ct. 10th,11th March,bay road Tower Hill OOC,track replcement work at Victoria,no service Whitechapel-Earl's Ct. 12th to 15th March,no service Turnham Grn-Richmond after 23:30 due to NR engineering work. 24th,25th March,bridgework between Chiswick Pk-Ravencourt Pk,no service West Ken-Acton Town/Richmond. 31st March,1st April,as above. 6th,7th,8th April,engineering work at Upton Pk,no service Plaistow-East Ham(also no H & C past Whitechapel). 14th,15th April,track replacement work at St James's Pk,no service Whitechapel-Earl's Ct. 21st April,bridgework at Chiswick Pk,no service Turnham Grn-Acton Town(District only). 28th,29th April,bridgework Chiswick Pk-Ravenscourt Pk,no service West Ken-Acton Town/Richmond. 12th,13th May,track replacement work at St James's Pk,no service Whitechapel-Earl's Ct.
|
|
|
Post by stanmorek on Jan 12, 2007 22:00:38 GMT
The bridge work I believe is related to civil and track enabling works required for the Class 66 locos on the District line.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jan 13, 2007 1:20:00 GMT
The 6th-8th April closure is the one for the trackbashers - it gets us the crossover at East Ham (FE).
|
|
towerman
My status is now now widower
Posts: 2,970
|
Post by towerman on Jan 13, 2007 1:33:15 GMT
I assume the reversing at West Ken will be via a main line shunt just west of the station.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jan 13, 2007 1:50:35 GMT
I assume the reversing at West Ken will be via a main line shunt just west of the station. I do hope so, I've never done that move!
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jan 13, 2007 15:22:07 GMT
that move at west ken may not be used they could just reverse them at olympia as this is far more reliable and if it does go pear shaped and the controller and signalman are not careful they could lock the site up (this has been done many times) as they cannot rely on the programme machines as they dont work at west ken for a west ken special (the t.d code for reversers)
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jan 13, 2007 18:39:22 GMT
Surely that only applies to east-to-west reversals? I would expect a west-to-east reversal to be relatively easy - simply run out of the station until one is behind RWC7, then change ends and wait for the shunt (WC33?) to drop...
|
|
towerman
My status is now now widower
Posts: 2,970
|
Post by towerman on Jan 13, 2007 21:27:35 GMT
It's a normal service between Olympia & Edgware Rd,reduced services on the rest of the line.
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Jan 13, 2007 22:23:30 GMT
same conditions still apply aswell as u cant have a train in the westbound platform whilst one is at the shunt (deffo not wc33) as this track locks the points
|
|